Crossroads Interchange Construction
Update for Week of July 6, 2015

Work scheduled:

  • Pouring concrete for eastbound on ramp onto I-44/I-49 during nighttime hours July 6
  • Grading along north side of I-44/I-49
  • Pouring concrete for widening of westbound I-44/I-49 lanes during nighttime hours July 8
  • Pouring concrete for Apple Road, Prigmor Avenue (CR 190) and south roundabout
  • Building forms to prepare for pouring of concrete for driving surface on new bridge
  • Pouring concrete for driving surface on new bridge morning of July 8
  • Grading base rock along north and south side of I-44/I-49

Traffic Impacts:

  • Right eastbound lane on I-44/I-49 CLOSED between 6 p.m., Monday, July 6 and 7 a.m., Tuesday, July 7 to pour concrete for eastbound on ramp
  • Right westbound lane on I-44/I-49 CLOSED between 6 p.m., Wednesday, July 8 and 7 a.m., Thursday, July 9 to pour concrete for widening of lanes
  • 20th Street at Prigmor Avenue (CR 190) CLOSED for duration of the project
  • Prigmor Avenue bridge (CR 190) CLOSED over I-44/I-49 until fall
  • Apple Road CLOSED at Prigmor Avenue (CR 190) for duration of the project. Drivers can access Apple Road via CR 180 and CR 170 north from Route FF (32nd Street)
  • Narrowed lanes on I-44/I-49 for the duration of the project
  • At least one lane of traffic open in each direction on I-44/I-49

Weather and/or construction delays will alter the work schedule.

Project Background:

  • Build interchange at Prigmor Avenue (Jasper County Road 190) over I-44/I-49 with ramps connecting to the interstate
  • Build roundabouts on each end of bridge over I-44/I-49 to connect ramps to Prigmor Avenue
  • Resurface and add two foot shoulders on Prigmor Avenue between new interchange and 7th Street (Route 66) to the north
  • Prime Contractor: Emery Sapp & Sons, Inc., Columbia
  • Total Project Cost: $8.6 million
  • Completion Date: November 1, 2015
  • Partnership Project: Jasper County, City of Duenweg, City of Joplin, Crossroads Business and Distribution Park

Project Map

RATE OUR WORK ZONE  

 

For more information, call MoDOT at 417-895-7600 or visit modot.org/southwest.

Follow MoDOT's Southwest District:

  • Facebook: MoDOT.Southwest
  • Twitter: MoDOT_Southwest
  • Google+: +MoDOT/Southwest District

 

 
District Map
Southwest District
spacer
Traveler Information
Traveler Map
Ozarks Traffic
map
call, cell, mobile, phone iconText Alerts - Sign Up!
spacer
Quick Links
Report a Road Concern
Media Inquiries
Your Local Area Engineer
Route 65: THE REBUILD
spacer
Your Local MoDOT
Get your local district information.
Districts Map
Northwest Northeast Kansas City Central St. Louis Southwest Southeast
About Us
How Do I...
Contact Us
Missouri Department of Transportation
Central Office
105 W. Capitol Avenue
Jefferson City, MO 65102
1-888-ASK-MODOT (275-6636)
1-866-831-6277 (Motor Carrier Services)
Drivers License Offices
horz_bar
| | |
Missouri State Government
 
© 2013 Missouri Department of Transportation. All Rights Reserved.   Privacy Policy.
 
 
Bates Vernon Barton Jasper Newton McDonald Barry Stone Taney Lawrence Dade Cedar St. Clair Henry Christian Greene Polk Hickory Benton Dallas Webster Northwest Northeast Kansas City Central St. Louis Southwest Southeast iTunes Android Facebook Twitter Flickr Instagram Blog YouTube RSS Facebook Twitter Flickr Google+ Blogspot YouTube RSS Feed