Route 13 Widening Project: Branson West to Kimberling City
Update for Week of March 26-30, 2012

Work scheduled:

  • Nighttime paving Route 13 between Joe Bald/James River Road and the Kimberling City bridge
  • Paving Stone Ridge Center Road
  • Laying asphalt for new driveway entrances and shoulders along Route 13 between Joe Bald/James River Road and Kimberling City
  • Hauling rock and dirt and grading for widening along Route 13 between Route OO and Joe Bald/James River Road
  • Grading dirt and rock for widening along Route 13 between Rollin Acres Road and Business 13 at Branson West
  • Building forms for the future deck of new Route 13 bridge at south edge of Stoneridge
  • Installing temporary traffic signals at Route OO and Route 13
  • Cleaning up areas around Lakeshore Drive at Route 13
  • Installing drain pipes across entrances from Route OO going north
  • Building temporary bypass at Rollin Acres Road

(Rain during the week of March 19 postponed much of the work until week of March 26)

Traffic Impacts:

  • NIGHT WORK: One-lane traffic in areas on Route 13 between Route OO and the Kimberling City bridge for asphalt paving and grading for widening work. Work hours: 7 p.m. to 6 a.m.
  • One-lane traffic on Stone Ridge Center Road 
  • One-lane traffic in areas during daytime hours. Work will take place at lower traffic volume times.
  • Business entrances may be closed one-half at a time
  • Temporary traffic signals to begin operation at Route OO
  • Short-term traffic stops at times on Route 13
  • Large equipment entering and leaving work areas
  • Work zone speed limit: 35 mph

(Weather or construction delays could alter the work schedule.)

Project Summary:

  • Widen Route 13 to four lanes between Branson West and Joe Bald/James River Road
  • Relocate a one-mile section of Route 13 west of Stoneridge
  • Install new traffic signals at Route 13 and Business 13 at the south edge of Branson West
  • Build right-turn and left-turn lanes in various locations
  • Build two new bridges

-- Route 13 at the south edge of Stoneridge

-- Armadillo Lane over new Route 13 at Stoneridge

  • Resurface existing Route 13 through Stoneridge business district
  • Resurface Route 13 between Joe Bald/James River Road and the Kimberling City bridge
  • Prime contractor: Journagan Construction of Springfield
  • Project cost: $11.5 million

Scheduled completion: December 2012

Links to related information:

 

 
District Map
Southwest District
spacer
Traveler Information
Traveler Map
Ozarks Traffic
map
call, cell, mobile, phone iconText Alerts - Sign Up!
spacer
Quick Links
Your Local Area Engineer
Report a Road Concern
Making History: I-49 in Missouri
On the Move
spacer
Your Local MoDOT
Get your local district information.
Districts Map
Northwest Northeast Kansas City Central St. Louis Southwest Southeast
About Us
How Do I...
Contact Us
Missouri Department of Transportation
Central Office
105 W. Capitol Avenue
Jefferson City, MO 65102
1-888-ASK-MODOT (275-6636)
horz_bar
| | |
Missouri State Government
 
© 2013 Missouri Department of Transportation. All Rights Reserved.   Privacy Policy.
 
 
Bates Vernon Barton Jasper Newton McDonald Barry Stone Taney Lawrence Dade Cedar St. Clair Henry Christian Greene Polk Hickory Benton Dallas Webster Northwest Northeast Kansas City Central St. Louis Southwest Southeast iTunes Android Facebook Twitter Flickr Pinterest Blog YouTube RSS