Project Facts:
- Replace bridges over Caney Creek, Kentucky Creek and Beaver Creek with new structures
- Build one bridge at a time, in this order: Kentucky, Beaver and Caney.
Construction: Summer 2017 until late 2018
Project Impacts:
Kentucky Creek bridge -- COMPLETED
- Build temporary bypass for Route 76 traffic
- Cost: $846,000
- Construction: Week of Sept. 25 until late December 2017
Beaver Creek bridge -- COMPLETED
- Close Route 76 at bridge
- Cost: $1.3 million
- Construction: early February until mid-June 2018
Caney Creek bridge -- COMPLETED
- Build temporary bypass for Route 76 traffic
- Cost: $981,000
- Construction: mid-June until early October 2018
Detour Route for Beaver Creek bridge Closing:
- Signed detour using Route 125, Christian County Route UU, Douglas County Route T and Route 76
- Length: 33 miles