Completed Projects
|
| |
| Crawford County |
BEFORE

X0758
|
AFTER

|
Bridge Location: Route M, Meramec River
Work to be completed: Deck replacement
Closure Duration: 60 days
Construction to Begin: September 14, 2009
Construction Complete: November 9, 2009
|
| |
|
| Howell County |
BEFORE

A0509 |
AFTER

|
Bridge Location: Route 17, Eleven Point River
Work completed: Deck replacement
Closure Duration: 53 days
Contractor: L. Krupp Construction, Inc., of Ellisville, Mo.
Construction Began: March 2, 2009
Construction Complete: April 23, 2009
|
|
| Phelps County |
BEFORE

A0524
|
AFTER |
Bridge Location: Route K, Spring Creek
Work to be completed: Deck replacement
Closure Duration: 60 days
Construction Began: May 26, 2009
Construction Complete: July 27 |
|
BEFORE

A1879
|
AFTER |
Bridge Location: Route M, Corn Creek
Work to be completed: Deck replacement
Closure Duration: 45 days
Construction to Begin: August 10, 2009
Construction Complete: September 15, 2009
|
| |
| Oregon County |
BEFORE

T0497
|
AFTER
 |
Bridge Location: Route E, Louse Creek
Work completed: Superstructure and deck replacement
Closure Duration: 45 days
Construction Began: March 31, 2009
Construction Complete: May 12, 2009 |
| |
| Washington County |
BEFORE

A0460
|
AFTER

|
Bridge Location: Route U, Big River
Work to be completed: Deck replacement
Closure Duration: 60 days
Construction Began: May 26, 2009
Construction Complete: July 24 |
|
|
BEFORE

R0444
|
AFTER |
Bridge Location: Route W, Brazil Creek
Work to be completed: Deck replacement
Closure Duration: 45 days
Construction to Begin: September 14, 2009
Construction Complete: October 27, 2009
|
|
| |
|
BEFORE

A0763
|
AFTER

|
Bridge Location: Route 185, Indian Creek
Work to be completed: Deck replacement
Closure Duration: 60 days
Construction to Begin: June 1, 2009
Construction Complete: July 30, 2009
|
| |
|
|
 |
 |
 |
 |
|
 |
 |