Project Information

   
Phelps County
   
3.1 miles north of Edgar Spings to Country Road 6330
Better Roads, Brighter Future Project

 

Project update:

During work hours the roadway will be reduced to one lane.

Construction began Dec. 4, 2007

This project was awarded at the The Missouri Highways and Transportation Commission

meeting held in June.

 

Location: 3.1 miles north of Edgar Springs to south of Route K
Length: 9.4 miles
Description: Add climbing/passing lanes and resurface the roadway

Contractor: Lake Asphalt Paving & Construction, LLC, Osage Beach, Mo.

Project Cost: $3,986,027

Construction Begin: December 2007
Construction Complete: July 2008
   