|
|
 |
 |
 |
 |
Value
Engineering Program
Purpose
The purpose of the program is to assure the public receives optimum value for every tax dollar invested in their transportation
system. The Value Engineering technique is used to improve
the department's productivity. Policy
FHWA
requires a value engineering study for all projects that exceed
25 million dollars and Bridge projects that exceed 20 million dollars. The department has a policy to study projects
that exceed 10 million dollars.
History
The program began in Federal Fiscal Year (October 1st to September 30th) 1988. That year ten
(10) projects under design were studied, with an estimated
construction cost savings of $8.8 million. During that year
48 employees were trained in value engineering concepts.
Including that first year and through Federal fiscal Year
2007, 229 value engineering studies have been completed
with an estimated cost savings of almost $330 million.
Construction VE
Beginning in late 1989 (Federal Fiscal Year 1990) the department
added a construction value engineering program. Contractors
submit Value Engineering Change Proposals (VECP'S) for department review and
approval. If accepted, the contractor and the department
share the total savings on a 50/50 basis. Beginning in 2007, contractors can submit VE/Practical Design Underruns (VE/PDU's). If accepted, VE/PDU savings are split 25% Contractor/75% MoDOT. VE/PDU's typically consist of an existing feature that could remain a part of the final project, for example, exisiting pavement, an existing pipe, etc. See file below for a summary of the Federal Fiscal Year 2007 Construction VECP's and VE/PDU's. Summary of FFY 2007 Construction VE's
Program Summary
|
Federal F.Y. |
No. of Studies |
Design Phase Savings |
Construction Phase Savings |
Department Cost |
Return on Investment |
1988 |
10 |
$8,800,000 |
$0 |
$49,000 |
180 |
1989 |
11 |
$3,200,000 |
$0 |
$125,000 |
26 |
1990 |
7 |
$8,100,000 |
$104,000 |
$65,000 |
126 |
1991 |
5 |
$6,800,000 |
$252,000 |
$92,000 |
77 |
1992 |
3 |
$5,900,000 |
$175,000 |
$73,000 |
83 |
1993 |
12 |
$4,100,000 |
$561,000 |
$147,000 |
32 |
1994 |
14 |
$13,000,000 |
$762,000 |
$164,000 |
84 |
1995 |
14 |
$6,200,000 |
$557,000 |
$165,000 |
41 |
1996 |
19 |
$13,100,000 |
$1,481,000 |
$245,000 |
60 |
1997 |
17 |
$7,620,000 |
$380,396 |
$159,411 |
50 |
1998 |
11 |
$12,190,000 |
$476,355 |
$146,976 |
86 |
1999 |
15 |
$2,700,000 |
$250,981 |
$249,272 |
12 |
2000 |
17 |
$9,645,000 |
$653,543 |
$278,239 |
37 |
2001 |
15 |
$17,300,000 |
$654,000 |
$179,288 |
100 |
2002 |
6 |
$37,000,000 |
$1,300,000 |
$119,950 |
319 |
2003 |
4 |
$13,900,000 |
$174,486 |
$52,160 |
270 |
2004 |
5 |
$8,060,000 |
$740,098 |
$66,928 |
131 |
2005 |
8 |
$59,929,000 |
$791,047 |
$104,353 |
582 |
2006 |
24 |
$39,786,000 |
$3,269,933 |
$194,939 |
221 |
2007 |
12 |
$52,348,000 |
$4,170,000 |
$82,309 |
687 |
Totals |
229 |
$329,678,000 |
$16,752,839 |
$2,758,825 |
126 |
|
|
| During the life
of this program, the department has documented savings totaling
over $330 million at a cost of less than $3 million; a rate of return
of $126 for every $1 invested.
|
|
| Awards and Recognition:
* 1997 FHWA Value Engineering Outstanding Achievement Award
* 1997 AASHTO VE Award for Most Innovative VE, ie., The
Grandview Triangle.
* 1999 AASHTO VE Award for Most Innovative VE Process,
ie., Traffic Communication Systems
|
|
 |
 |
 |
 |
| |
|
| |
|
|