|
The Safe & Sound Bridge Program in Northwest Missouri improved 190 bridges. The program began in 2008 and was completed in 2012 ahead of schedule. In just slightly more than 3-and-a-half years a project that was expected to take more than five years has been completed. And as a result, Missourians in every county of the state are driving across new and improved bridges that will serve their needs for many years to come.
The $685 million Safe & Sound Bridge Improvement Program drew to a close on November 8 with a ribbon-cutting ceremony on the Route 11 bridge over the BNSF Railroad in Chariton County. At the event, Missouri Highways and Transportation Commission Chairman Rudy Farber said, “
"This was a fabulous program - the biggest bridge program in Missouri history. It’s really hard to imagine – 802 new or improved bridges in just 3-1/2 years.”
|

190 Bridges In
Northwest Missouri
Now Completed
|
|
PROJECT COMPLETE
 
Before After
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 59 Hwy. / Bus. 71 Hwy. (northbound)
Bridge location: at Interstate 29
Work to be done: Bridge redeck
Originally built: 1962
Awarded on: May 11, 2010
Award amount: $1,816.999.30 (Includes work on north & southbound bridges)
Awarded to: Loch Sand & Construction, Co.
Construction begins: June 14, 2010
Closure date: July 21, 2010
Construction complete: November 2, 2010
Route: U.S. 59 Hwy. / Bus. 71 Hwy. (southbound)
Bridge location: at Interstate 29
Work to be done: Bridge redeck
Originally built: 1962
Awarded on: May 11, 2010
Award amount: $1,816.999.30 (Includes work on north & southbound bridges)
Awarded to: Loch Sand & Construction, Co.
Construction begins: June 14, 2010
Closure date: September 8, 2010
Construction complete: November 2, 2010
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 169 Hwy.
Bridge location: Niagara Creek
Work to be done: Bridge replacement
Originally built: 1928
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: July 23, 2012
Construction complete: August 11, 2012 (Closed 19 days)
Detour map: Andrew Route 169 Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 48
Bridge location: MO 48 at Platte River Overflow
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: May 16, 2011
Construction completed: June 22, 2011 (Closed 37 days) Detour map: Click here for MO 48 Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route H
Bridge location: Pedlar Creek
Work to be done: Bridge redeck
Originally built: 1954
Awarded on: December 5, 2008
Award amount: $208,455.90
Awarded to: Boone Construction Company
Closure date: April 6, 2009
Construction completed: May 20, 2009 (Closed 44 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route DD
Bridge location: Dillon Creek
Work to be done: Bridge replacement
Originally built: 1958
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 21, 2010
Construction completed: August 24, 2010 (Closed 65 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route Y
Bridge location: Owl Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 16, 2011
Construction completed: June 28, 2011 (Closed 44 days) Detour map: Click here for Route Y Detour
|
| |
|
|
PROJECT COMPLETE

Before After
|
|
Route: Route H
Bridge location: Arapahoe Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 7, 2010
Construction completed: October 28, 2010 (Closed 51 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route A
Bridge location: drainage ditch
Work to be done: Bridge replacement
Originally built: 1930
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 6, 2011
Construction completed: August 15, 2011 (Closed 39 days)
Detour map: Click here for Route A Detour
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 59 Hwy.
Bridge location: at Tarkio River
Work to be done: Bridge replacement
Originally built: 1936
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: January 30, 2012 Construction completed: April 16, 2012 (Closed 77 days ) Detour Map: Click here for U.S. 59 Hwy. Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 136 Hwy.
Bridge location: Cow Creek
Work to be done: Bridge replacement
Originally built: 1946
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 21, 2012
Construction completed: July 3, 2012 (Closed 43 days)
Detour Map:Click here for US 136 Hwy. Detour |
PROJECT COMPLETE
 
Before After |
|
Route: MO 46
Bridge location: Hickory Creek
Work to be done: Bridge replacement
Originally built: 1936
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 14, 2012
Construction completed: June 15, 2012 (Closed 32 days)
Detour Map: Click here for MO 46 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 46
Bridge location: Little Tarkio Drainage Ditch
Work to be done: Bridge replacement
Originally built: 1935
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: June 3, 2011
Construction completed: August 11, 2011 (Closed 65 days)
Detour Map: Click here for MO 46 Detour |
| |
|
|
PROJECT COMPLETE  
Before After |
|
Route: U.S. 275 Hwy.
Bridge location: Kings Bridge
Work to be done: Bridge redeck
Originally built: 1951
Awarded on: March 4th
Award amount: $255,037.80
Awarded to: A.M. Cohron & Sons, Inc.
Closure date: June 1, 2009
Construction completed: July 27, 2009 (Closed 53 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route C
Bridge location: Mid Tarkio Creek
Work to be done: Bridge replacement
Originally built: 1938
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 31, 2011
Construction completed: August 3, 2011 (Closed 63 days)
Detour Map: Click here for Route C Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route C
Bridge location: Tarkio River
Work to be done: Bridge replacement
Originally built: 1938
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 4, 2011
Construction completed: October 18, 2011 (Closed 74 days)
Detour Map: Click here for Route C Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route M
Bridge location: Long Branch Creek
Work to be done: Bridge redeck
Originally built: 1961
Awarded on: March 4th
Award Amount: $216,274.78
Awarded to: A.M. Cohron & Sons, Inc.
Closure Date: April 7, 2009
Construction completed: May 28, 2009 (Closed 50 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route V
Bridge location: Main Drainage Ditch #6
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 14, 2011
Construction completed: May 23, 2011 (Closed 71 days)
Detour Map: Click here for Route V Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route B
Bridge location: Halls Branch
Work to be done: Bridge replacement
Originally built: 1930
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 3, 2011
Construction completed: June 17, 2011 (Closed 46 days)
Detour Map: Click here for Route B Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 46
Bridge location: East Fork Hickory Creek
Work to be done: Bridge replacement
Originally built: 1936
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 15, 2011
Construction completed: September 14, 2011 (Closed 29 days)
Detour Map: Click here for MO 46 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 111
Bridge location: Turkey Creek
Work to be done: Bridge replacement
Originally built: 1936
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: November 7, 2011
Construction completed: December 9, 2011 (Closed 32 days)
Detour Map: Click here for MO 111 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 111
Bridge location: Drainage Ditch
Work to be done: Bridge replacement
Originally built: 1936
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: October 31, 2011
Construction completed: December 9, 2011 (Closed 39 days)
Detour Map: Click here for MO 111 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route B
Bridge location: Rock Creek
Work to be done: Bridge replacement
Originally built: 1948
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 12, 2011
Construction completed: October 25, 2011 (Closed 43 days)
Detour Map: Click here for Route B Detour
|
PROJECT COMPLETE
 
Before After |
|
Route: Route O
Bridge location: Interstate 29
Work to be done: Bridge redeck
Originally built: 1958
Community briefing held: Tuesday, February 24, 2009
Awarded on: April 1, 2009
Award amount: $401,870.00
Awarded to: Clarkson Construction Company
Closure date: September 8, 2009
Construction completed: October 9, 2009 (Closed 30 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: U.S. 169 Hwy.
Bridge location: Interstate 29
Work to be done: Bridge redeck
Originally built: 1962
Community briefing held: Thursday, February 26, 2009
Awarded on: April 1, 2009
Award amount: $1,067,858.00
Awarded to: Clarkson Construction Company
Closure date: July 10, 2009
Construction completed: August 25, 2009 (Closed 48 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route CC
Bridge location: South Fork of Bee Creek
Work to be done: Bridge redeck
Originally built: 1969
Community briefing held: Tuesday, February 24, 2009
Awarded on: April 1, 2009
Award amount: $326,088.40
Awarded to: Clarkson Construction Company
Closure date: June 8, 2009
Construction completed: July 18, 2009 (Closed 41 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 59 Hwy.
Bridge location: Cloverdale Ditch
Work to be done: Bridge replacement
Originally built: 1941
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 19, 2012
Construction completed: May 3, 2012 (Closed 45 days)
Detour Map: Click here for US 59 Hwy. Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 59 Hwy.
Bridge location: Gay Branch
Work to be done: Bridge replacement
Originally built: 1920
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 19, 2012
Construction completed: May 3, 2012 (Closed 45 days)
Detour Map: Click here for US 59 Hwy. Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 116
Bridge location: Lost Creek
Work to be done: Bridge replacement
Originally built: 1950
Awarded to: KTU Constructors (Design-Build Contract)
Closure date June 18, 2012
Construction completed: July 20, 2012 (Closed 33 days)
Detour Map: Click here for MO 116 Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route M
Bridge location: Sugar Creek
Work to be done: Bridge replacement
Originally built: 1956
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 25, 2012
Construction completed: August 11, 2012 (Closed 47 days)
Detour Map: Click here for Route M Detour
|
| |
|
|
PROJECT COMPLETE

Before |
|
Route: Route DD
Bridge location: Malden Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 23, 2012
Construction completed: August 25, 2012 (Closed 32 days)
Detour Map: Click here for Route DD Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 116
Bridge location: Bee Creek
Work to be done: Bridge replacement
Originally built: 1933
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 19, 2012
Construction completed: April 26, 2012 (Closed 38 days)
Detour Map: Click here for MO 116 Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 116
Bridge location: Little Bee Creek
Work to be done: Bridge replacement
Originally built: 1933
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 14, 2012
Construction completed: June 13, 2012 (Closed 30 days)
Detour Map: Click here for MO 116 Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route P
Bridge location: Third Fork of Platte River
Work to be done: Bridge replacement
Originally built: 1934
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: March 12, 2012
Construction completed: April 26, 2012 (Closed 44 days)
Detour Map: Click here for Route P Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route KK
Bridge location: Puckett Slu
Work to be done: Bridge replacement
Originally built: 1936
Awarded on: May, 2009
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 19, 2009
Construction completed: November 10, 2009 (Closed 22 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route H
Bridge location: Wolfpen Creek
Work to be done: Bridge replacement
Originally built: 1948
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 3, 2011
Construction completed: November 3, 2011 (Closed 30 days)
Detour Map: Click here for Route H Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: US 36 Hwy. (westbound)
Bridge location: Union Pacific Railroad Bridge
Work to be done: Bridge replacement
Originally built: 1958
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: April 30, 2012
Construction completed: June 23, 2012 (Closed 54 days)
Detour map: Click here for U.S. 36 Hwy. Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 116
Bridge location: N. Mud Creek
Work to be done: Bridge redeck
Originally built: 1964
Awarded on: September 2, 2009
Award amount: $267,963.00
Awarded to: Chester Bross Cons. Co./C.B. Equipment, Inc.
Closure date: April 5, 2010
Construction Completed: May 20th 2010 (Closed 45 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route A
Bridge location: Dead Oak Creek
Work to be done: Bridge redeck
Originally built: 1966 Awarded on: September 2, 2009
Award amount: $177,808.50
Awarded to: Chester Bross Cons. Co./C.B. Equipment, Inc.
Closure date: May 24, 2010
Construction Completed: June 23, 2010 (Closed 29 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route W
Bridge location: East Sheep Creek
Work to be done: Bridge replacement
Originally built: 1923
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 7, 2012
Construction Completed: June 6, 2012 (Closed 30 days)
Detour map: Click here for Route W Detour
 |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route N
Bridge location: Mud Creek
Work to be done: Bridge redeck
Originally built: 1958 Awarded on: September 2, 2009
Award amount: $236,095.00
Awarded to: Chester Bross Cons. Co./C.B. Equipment, Inc.
Closure date: April 19, 2010
Construction completed: June 4, 2010 (Closed 47 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route U
Bridge location: Otter Creek
Work to be done: Bridge redeck
Originally built: 1960
Awarded to: Widel Inc.
Closure date: April 25, 2011
Construction completed: June 29, 2011 (Closed 65 days)
Detour map: Click here for Route U Detour
 |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route D
Bridge location: Goose Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract) Closure date: April 23, 2012
Construction completed: May 30, 2012 (Closed 38 days)
Detour map: Click here for Route D Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route HH
Bridge location: Plum Creek
Work to be done: Bridge redeck
Originally built: 1965
Awarded to: Widel Inc.
Closure date: June 1, 2011
Construction completed: July 15, 2011 (Closed 44 days)
Detour map: Click here for Route HH Detour
 |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route A
Bridge location: Panther Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: April 2, 2012
Construction completed: May 10, 2012 (Closed 39 days)
Detour map: Click here for Route A Detour
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route E
Bridge location: Fish Pond Creek
Work to be done: Bridge replacement
Originally built: 1946
Awarded to: KTU Constructors (Design-Build Contract) Closure date: June 25, 2010
Construction completed: July 24, 2010 (Closed 37 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route E
Bridge location: McCroskie Creek
Work to be done: Bridge replacement
Originally built: 1946
Awarded to: KTU Constructors (Design-Build Contract) Closure date: April 25, 2010
Construction completed: July 3, 2010 (Closed 84 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route B
Bridge location: Camp Creek
Work to be done: Bridge replacement
Originally built: 1951
Awarded to: KTU Constructors (Design-Build Contract) Closure date: April 25, 2010
Construction completed: May 24, 2010 (Closed 36 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route B
Bridge location: Camp Creek
Work to be done: Bridge replacement
Originally built: 1930
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 19, 2010
Construction completed: June 30, 2010 (Closed 35 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route OO
Bridge location: McCroskie Creek
Work to be done: Bridge replacement
Originally built: 1956
Awarded to: KTU Constructors (Design-Build Contract) Closure date: July 19, 2010
Construction completed: August 27, 2010 (Closed 37 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route M
Bridge location: Big Creek
Work to be done: Bridge replacement
Originally built: 1958
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 28, 2010
Construction completed: August 20, 2010 (Closed 53 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route M
Bridge location: Bridge Creek
Work to be done: Bridge deck replacement
Originally built: 1958
Awarded to: Widel, Inc.
Closure date: September 2, 2009
Construction completed: October 30, 2009 (Closed 59 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route M
Bridge location: Wolf Creek
Work to be done: Bridge replacement
Originally built: 1958
Awarded to: KTU Constructors (Design-Build Contract) Closure date: April 4, 2011
Construction completed: May 3, 2011 (Closed 36 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route W
Bridge location: Burr Oak Creek
Work to be done: Bridge replacement
Originally built: 1955
Awarded to: KTU Constructors (Design-Build Contract) Closure date: May 14, 2011
Construction completed: July 1, 2010 (Closed 46 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route 139
Bridge location: Big Creek Overflow
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 18, 2010
Construction completed: November 24, 2010 (Closed 114 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route 139
Bridge location: Big Creek Drainage Ditch
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract) Closure date: August 18, 2010
Construction completed: November 24, 2010 (Closed 114 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route 139
Bridge location: Big Creek
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract) Closure date: August 18, 2010
Construction completed: November 24, 2010 (Closed 114 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route J
Bridge location: Mound Creek
Work to be done: Bridge replacement
Originally built: 1934
Awarded to: KTU Constructors (Design-Build Contract) Closure date: April 12, 2010
Construction completed: May 21, 2010 (Closed 43 days) |
PROJECT COMPLETE

|
|
Route: MO 11
Bridge location: BNSF
Work to be done: Bridge replacement
Originally built: 1936
Awarded to: KTU Constructors (Design-Build Contract) Closure date: September 4, 2012
Construction completed: November 9, 2012 (Closed 60 days)
|
PROJECT COMPLETE
 
Before After |
|
Route: Route P
Bridge location: Puzzle Creek
Work to be done: Bridge replacement
Originally built: 1948
Awarded to: KTU Constructors (Design-Build Contract) Closure date: March 7, 2011
Construction completed: April 14, 2011 (Closed 53 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route PP
Bridge location: New Hope Creek
Work to be done: Bridge replacement
Originally built: 1959
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 12, 2011 Construction completed: October 18, 2011 (Closed 36 days) Detour Map: Click here for Route PP Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route K
Bridge location: Castile Creek
Work to be done: Bridge redeck
Originally built: 1960
Awarded to: Widel Inc.
Closure date: February 28, 2011
Construction complete: April 29, 2011 (Closed 59 days)
Detour Map: Click here for Route K Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route V
Bridge location: Interstate 35
Work to be done: Bridge redeck
Originally built: 1964
Awarded to: Widel Inc.
Closure date: March 14, 2011
Construction complete: May 6, 2011 (Closed 52 days)
Detour Map: Click here for Route V Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 121
Bridge location: Deer Creek
Work to be done: Bridge replacement
Originally built: 1935
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 10, 2011
Construction complete: November 10, 2011 (Closed 30 days)
Detour Map: Click here for MO 121 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route NN
Bridge location: McGuire Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 7, 2012
Construction complete: June 8, 2012 (Closed 33 days)
Detour Map: Click here for Route NN Detour |
PROJECT COMPLETE
 
Before After |
|
Route: Route RA
Bridge location: East Brushy Creek
Work to be done: Bridge redeck
Originally built: 1972
Awarded on: January 8, 2009
Award amount: $299,419.00
Awarded to: Chester Bross Construction Company
Closure date: May 26, 2009
Construction completed: June 30, 2009 (Closed 35 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 13
Bridge location: Little Cypress Creek
Work to be done: Bridge replacement
Originally built: 1937
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: October 31, 2011
Construction completed: December 13, 2011 (Closed 43 days)
Detour Map: Click here for MO 13 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route T
Bridge location: Sampson Creek
Work to be done: Bridge redeck
Originally built: 1957
Awarded to: Comanche Construction Inc.
Award amount: $750,543.90
Closure date: March 7, 2011
Construction completed: April 27, 2011 (Closed 50 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route CC
Bridge location: Dog Creek
Work to be done: Bridge bridge replacement
Originally built: 1953
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 12, 2012
Construction completed: April 24, 2012 (Closed 44 days)
Detour Map: Click here for Route CC Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route P
Bridge location: Pilot Grove Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 28, 2011
Construction completed: May 10, 2011 (Closed 42 days)
Detour Map: Click here for Route P Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route P
Bridge location: Big Muddy Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 6, 2011
Construction completed: October 14, 2011 (Closed 38 days)
Detour Map: Click here for Route P Detour
 |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route E
Bridge location: Grindstone Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: April 2, 2012
Construction completed: May 24, 2012 (Closed 53 days)
Detour Map: Click here for Route E Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route V
Bridge location: Muddy Creek
Work to be done: Bridge redeck
Originally built: 1963
Awarded to: Widel, Inc.
Closure date: July 12, 2011
Construction completed: September 6, 2011 (Closed 54 days)
Detour Map: Click here for Route V Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route Z
Bridge location: Drainage ditch
Work to be done: Bridge redeck
Originally built: 1961
Awarded to: Widel, Inc.
Closure date: June 28, 2011
Construction completed: August 23, 2011 (Closed 55 days)
Detour Map: Click here for Route Z Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route HH
Bridge location: Marrowbone Creek
Work to be done: Bridge redeck
Originally built: 1962
Awarded to: Widel, Inc.
Closure date: August 23, 2011
Construction completed: October 20, 2011 (Closed 57 days)
Detour Map: Click here for Route HH Detour
 |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route J
Bridge location: Dog Creek
Work to be done: Bridge replacement
Originally built: 1931
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 29, 2012
Construction completed: July 2, 2012 (Closed 34 days)
Detour Map: Click here for Route J Detour
 |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route K
Bridge location: East Creek
Work to be done: Bridge replacement
Originally built: 1934
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 16, 2011
Construction completed: June 9, 2011 (Closed 23 days)
Detour Map: Click here for Route K Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route K
Bridge location: Pilot Grove Creek
Work to be done: Bridge replacement
Originally built: 1934
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 6, 2011
Construction completed: July 1, 2011 (Closed 25 days)
Detour Map: Click here for Route K Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route J
Bridge location: Marrowbone Creek
Work to be done: Bridge replacement
Originally built: 1935
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 18, 2012
Construction completed: July 23, 2012 (Closed 36 days)
Detour Map: Click here for Route J Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route M
Bridge location: Lick Fork Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: August 8, 2011
Construction completed: September 19, 2011 (Closed 41 days)
Detour Map: Click here for Route M Detour
 |
PROJECT COMPLETE
 
Before After
|
|
Route: MO 33
Bridge location: Branch of Lost Creek (Red Horse Creek)
Work to be done: Bridge redeck
Originally built: 1959
Awarded on: December 2, 2009
Award amount: $258,526.93
Awarded to: Loch Sand & Construction Co.
Closure date: March 22, 2010
Construction completed: April 27, 2010 (Closed 36 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: MO 33
Bridge location: West Fork Lost Creek
Work to be done: Bridge redeck
Originally built: 1959
Awarded on: December 2, 2009
Award amount: $252,744.35
Awarded to: Loch Sand & Construction Co.
Closure date: April 27, 2010
Construction completed: June 3, 2010 (Closed 37 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 36 Hwy. (westbound)
Bridge location: Castile Creek
Work to be done: Bridge replacement
Originally built: 1923
Awarded to: KTU Constructors (Design-Build Contract) Closure date: May 4, 2011
Construction completed: June 16, 2011 (Closed 42 days)
Detour map: Click here for U.S. 36 Hwy. Westbound Detour |
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 36 Hwy. (eastbound)
Bridge location: Castile Creek
Work to be done: Bridge redeck
Originally built: 1966 Closed for construction: July 18, 2011
Construction completed: September 9, 2011 (Closed 51 days)
Detour map: Click here for U.S. 36 Hwy. Eastbound Detour
|
|
|
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 36 Hwy. (westbound)
Bridge location: Grindstone Creek
Work to be done: Bridge redeck
Originally built: 1966 Closed for construction: August 29, 2011
Construction completed: October 12, 2011 (Closed 43 days)
Detour map: Click here for U.S. 36 Hwy. Westbound Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route A
Bridge location: East Fork Lost Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract) Closed for construction: October 17, 2011
Construction completed: December 6, 2011 (Closed 49 days)
Detour map: Click here for Route A Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route E
Bridge location: North Fork Lost Creek
Work to be done: Bridge redeck
Originally built: 1956
Awarded on: January 8, 2009
Award amount: $227,405.00
Awarded to: St. Joseph Fuel Oil & Mfg. Co.
Closure date: June 22, 2009
Construction completed: August 6, 2009 (Closed 45 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route V
Bridge location: Third Fork Platte River
Work to be done: Bridge redeck
Originally built: 1957
Award amount: $277,330.00
Awarded to: St. Joseph Fuel Oil & Mfg. Co.
Closure date: March 30, 2009
Construction completed: May 14, 2009 (Closed 46 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route F
Bridge location: Crooked Creek
Work to be done: Bridge redeck
Originally built: 1961 Award amount: $291,606.84 Awarded to: Chester Bross Const. Co. / C.B. Equipment Inc. Closure date: August 29, 2011 Construction completed: October 21, 2011 (Closed 52 days)
Detour map: Click here for Route F Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route C
Bridge location: Grindstone Creek
Work to be done: Bridge redeck
Originally built: 1952
Awarded on: January 8, 2009
Award amount: $271,372.00
Awarded to: St. Joseph Fuel Oil & Mfg. Co.
Closure date: May 11, 2009
Construction completed: June 25, 2009 (Closed 45 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route H
Bridge location: Dry Branch
Work to be done: Bridge replacement
Originally built: 1953
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 26, 2011
Construction completed: October 20, 2011
Detour map: Click here for Route H Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route J
Bridge location: Abandoned Railroad Bridge
Work to be done: Bridge removal
Originally built: 1964
Awarded on: May 11, 2010
Award amount: $178,145.79
Awarded to: Widel, Inc.
Closure date: August 2, 2010
Construction completed: September 14, 2010 (Closed 44 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route E
Bridge location: Little Third Fork Platte
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: November 7, 2011
Construction completed: December 14, 2011 (Closed 37 days)
Detour map: Click here for Route E Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route E
Bridge location: Lost Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract) Closure date: May 14, 2012
Construction completed: June 21, 2012 (Closed 38 days)
Detour map: Click here for Route E Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route E
Bridge location: East Fork Lost Creek
Work to be done: Bridge replacement
Originally built: 1941
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: June 11, 2012
Construction completed: July 18, 2012 (Closed 38 days)
Detour map: Click here for Route E Detour
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 169 Hwy.
Bridge location: Old Channel Island Creek
Work to be done: Bridge removal
Originally built: 1941
Closure date: April 3, 2012
Construction completed: April 11, 2012 (Closed 9 days)
Detour Map: Click here for US 169 Hwy. Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 85
Bridge location: Thompson Branch
Work to be done: Bridge redeck
Originally built: 1925
Closure date: January 25, 2012
Construction completed: April 7, 2012 (Closed 73 days)
Detour Map: Click here for MO 85 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 85
Bridge location: Town Creek
Work to be done: Bridge replacement
Originally built: 1925
Awarded to: KTU Constructors (Design-Build Contract) Closure date: May 31, 2011
Construction completed: July 8, 2011 (Closed 37 days)
Detour Map: Click here for MO 85 Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 136 Hwy.
Bridge location: Town Branch
Work to be done: Bridge replacement
Originally built: 1929
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 6, 2011
Construction completed: July 20, 2011 (Closed 44 days) Detour Map: Click here for U.S. 136 Hwy. Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 136 Hwy.
Bridge location: Moccasin Creek
Work to be done: Bridge replacement
Originally built: 1929
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: August 15, 2011
Construction completed: October 3, 2011 (Closed 48 days)
Detour Map: Click here for U.S. 136 Hwy. Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route UU
Bridge location: Turkey Creek
Work to be done: Bridge replacement
Originally built: 1958
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 7, 2010
Construction completed: October 30, 2010 (Closed 53 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route BB
Bridge location: Island Creek
Work to be done: Bridge redeck
Awarded on: January 9, 2009
Award amount: $230,416.00
Awarded to: Chester Bross Construction Company
Closure date: June 8, 2009
Construction completed: July 10, 2009 (Closed 33 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route O
Bridge location: West Fork Grand River
Work to be done: Bridge replacement
Originally built: 1960
Awarded to: KTU Constructors (Design-Build Contract) Closure date: February 9, 2011
Construction completed: May 11, 2011 (Closed 90 days)
Detour Map: Click here for Route O Detour |
| |
|
|
PROJECT COMPLETE  
Before After |
|
Route: Route A
Bridge location: Evona Creek
Work to be done: Bridge replacement
Originally built: 1930
Awarded to: KTU Constructors (Design-Build Contract) Closure date: October 11, 2010
Construction completed: November 11, 2010 (Closed 30 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route H
Bridge location: West Fork Grand River
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: August 15, 2011
Construction completed: October 12, 2011 (Closed 57 days)
Detour Map: Click here for Route H Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route M
Bridge location: Island Creek
Work to be done: Bridge replacement
Originally built: 1948
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 14, 2011
Construction completed: May 4, 2011 (Closed 51 days)
Detour Map: Click here for Route M Detour
|
PROJECT COMPLETE
 
Before After |
|
Route: Route WW
Bridge location: Hickory Creek
Work to be done: Bridge replacement
Originally built: 1955
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 24, 2010
Construction completed: October 13, 2010 (Closed 47 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route E
Bridge location: Crooked Creek
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 13, 2010
Construction completed: October 5, 2010 (Closed 35 days) |
PROJECT COMPLETE
 
Before After
|
|
Route: U.S. 69 Hwy
Bridge location: Big Creek
Work to be done: Bridge replacement
Originally built: 1928
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 13, 2010
Construction completed: November 10, 2010 (Closed 57 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: U.S. 69 Hwy.
Bridge location: Big Creek Overflow
Work to be done: Bridge replacement
Originally built: 1928
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 4, 2010 Construction completed: November 10, 2010 (Closed 36 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 136 Hwy.
Bridge location: Sugar Creek
Work to be done: Bridge replacement
Originally built: 1937
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 18, 2011
Construction completed: August 17, 2011 (Closed 29 days)
Detour map: Click here for U.S. 136 Hwy. Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route MM
Bridge location: Fox Creek
Work to be done: Bridge redeck
Originally built: 1962
Award amount: $135,150.00
Awarded to: Chester Bross Construction Co.
Closure date: August 10, 2010
Construction completed: September 21, 2010 (Closed 42 days)
Detour map: Click here for Route MM Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route M
Bridge location: Big Muddy Creek
Work to be done: Bridge redeck
Originally built: 1957
Award amount: $234,973.32
Awarded to: Loch Sand and Construction Co.
Closure Date: May 6, 2009
Construction completed: June 9, 2009 (Closed 34 days)
Bridge Painting Project: Scheduled For 2010
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route UU
Bridge location: Indian Creek
Work to be done: Bridge replacement
Originally built: 1958
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: November 1, 2010
Construction completed: December 23, 2010 (Closed 52 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route KK
Bridge location: Shain Creek
Work to be done: Bridge replacement
Originally built: 1959
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: April 26, 2010
Construction completed: June 9, 2010 (Closed 44 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route HH
Bridge location: Lotts Creek
Work to be done: Bridge redeck
Originally built: 1960
Award amount: $268,942.92
Awarded to: Loch Sand and Construction Co.
Closure date: May 26, 2009
Construction completed: July 8, 2009 (Closed 43 days) Bridge Painting Project: Scheduled For 2010
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route MM
Bridge location: Sugar Creek
Work to be done: Bridge redeck
Originally built: 1962
Award amount: $174,338.00
Awarded to: Chester Bross Construction Co.
Closure date: September 20, 2010
Construction completed: October 29, 2010 (Closed 39 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route N
Bridge location: Brush Creek
Work to be done: Bridge replacement
Originally built: 1950
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: April 12, 2010
Construction Completed: June 1, 2010 (Closed 51 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route O
Bridge location: Indian Creek
Work to be done: Bridge replacement
Originally built: 1950
Awarded to: KTU Constructors (Design-Build Contract)
Closure date : August 16, 2010
Construction completed: September 24, 2010 (Closed 39 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route O
Bridge location: Donaby Creek
Work to be done: Bridge replacement
Originally built: 1950
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 6, 2010
Construction Completed: August 13, 2010 (Closed 38 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route F
Bridge location: Panther Creek
Work to be done: Bridge replacement
Originally built: 1951
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 22, 2010
Construction completed: October 28, 2010 (Closed 36 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route CC
Bridge location: Cat Creek
Work to be done: Bridge replacement
Originally built: 1953
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 10, 2011
Construction completed: November 4, 2011 (Closed 24 days)
Detour map: Click here for Route CC Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route Z
Bridge location: Shain Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 14, 2010
Construction completed: September 3, 2010 (Closed 51 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route M
Bridge location: West Fork Big Creek
Work to be done: Bridge replacement
Originally built: 1955
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 18, 2010
Construction completed: October 5, 2010 (Closed 49 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route Y
Bridge location: Trail Creek
Work to be done: Bridge replacement
Originally built: 1956
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 7, 2010
Construction completed: November 24, 2010 (Closed 47 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route AA
Bridge location: Big Creek
Work to be done: Bridge redeck
Originally built: 1962
Award amount: $353,788.00
Awarded to: Chester Bross Construction Co.
Closure date: August 30, 2010
Construction completed: October 29, 2010 (Closed 60 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route B
Bridge location: BR
Work to be done: Bridge replacement
Originally built: 1931
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 7, 2010
Construction completed: July 12, 2010 (Closed 36 days)
|
|
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route B
Bridge location: Panther Creek
Work to be done: Bridge replacement
Originally built: 1931
Awarded to: KTU Constructors (Design-Build Contract)
Closure Date : July 19, 2010
Construction completed: August 25, 2010 (Closed 38 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route B
Bridge location: Drainage Ditch
Work to be done: Bridge replacement
Originally built: 1931
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 25, 2010
Construction completed: June 23, 2010 (Closed 30 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 46
Bridge location: West Fork Big Creek
Work to be done: Bridge replacement
Originally built: 1946
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 25, 2012
Construction completed: August 8, 2012 (Closed 44 days)
Detour map: Click here for MO 46 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 46
Bridge location: East Fork Big Creek
Work to be done: Bridge replacement
Originally built: 1946
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 1, 2010
Construction completed: July 23, 2010 (Closed 53 days) |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 46
Bridge location: Shain Creek
Work to be done: Bridge replacement
Originally built: 1946
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 22, 2010
Construction completed: May 14, 2010 (Closed 54 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route A
Bridge location: Big Panther Creek
Work to be done: Bridge replacement
Originally built: 1949
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: April 5, 2010
Construction completed: May 18, 2010 (Closed 44 days)
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 59 Hwy.
Bridge location: Little Tarkio Creek
Work to be done: Bridge replacement
Originally built: 1926
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: August 22 , 2011
Construction completed: October 11, 2011 (Closed 49 days)
Detour map: Click here for US 59 Hwy. Detour
 |
| |
|
|
PROJECT COMPLETE
 
Before After
PROJECT COMPLETE
 
Before After
|
|
Route: Route B
Bridge location: Nichols Creek (South)
Work to be done: Bridge replacement
Originally built: 1953
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: April 4, 2011
Construction completed: May 9, 2011 (Closed 35 days)
Detour map: Click here for Route B Detour
Route: Route B
Bridge location: Nichols Creek (North)
Work to be done: Bridge replacement
Originally built: 1931
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: May 9, 2011
Construction completed: June 29, 2011 (Closed 51 days)
Detour map: Click here for Route B Detour
|
PROJECT COMPLETE
 
Before After |
|
Route: Route B
Bridge location: Lincoln Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: June 27, 2011
Construction completed: August 24, 2011 (Closed 55 days)
Detour map: Click here for Route B Detour |
PROJECT COMPLETE
 
Before After |
|
Route: MO 111
Bridge location: Old Channel of Big Tarkio
Work to be done: Bridge replacement
Originally built: 1956
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: April 16, 2012
Construction completed: May 22, 2012 (Closed 37 days)
Detour map: Click here for MO 111 Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 111
Bridge location: Cannon Creek
Work to be done: Bridge replacement
Originally built: 1956
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: March 5, 2012
Construction completed: April 4, 2012 (Closed 30 days)
Detour map: Click here for MO 111 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route C
Bridge location: Mid Branch of Squaw Creek
Work to be done: Bridge replacement
Originally built: 1955
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: March 19, 2012
Construction completed: May 1, 2012 (Closed 43 days)
Detour map: Click here for Route C Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route C
Bridge location: Squaw Creek
Work to be done: Bridge replacement
Originally built: 1955
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 3, 2011
Construction completed: November 1, 2011 (Closed 28 days)
Detour map: Click here for Route C Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route N
Bridge location: East Branch of Squaw Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 21, 2011
Construction completed: May 27, 2011 (Closed 67 days)
Detour map: Click here for Route N Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route N
Bridge location: Mid Branch of Squaw Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 26, 2011
Construction completed: July 18, 2011 (Closed 53 days)
Detour map: Click here for Route N Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: MO 111
Bridge location: Corn Creek
Work to be done: Bridge replacement
Originally built: 1936
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: April 11, 2011
Construction completed: May 26, 2011 (Closed 45 days)
Detour map: Click here for MO 111 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route C
Bridge location: Wildcat Creek
Work to be done: Bridge replacement
Originally built: 1949
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: September 6, 2011
Construction completed: October 5, 2011 (Closed 29 days)
Detour map: Click here for Route C Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route C
Bridge location: Minnesota Valley Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 18, 2011
Construction completed: September 2, 2011 (Closed 45 days)
Detour map: Click here for Route C Detour |
PROJECT COMPLETE
 
Before After
|
|
Route: DD
Bridge location: Parsons Creek
Work to be done: Bridge replacement
Originally built: 1951
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 27, 2010
Construction completed: October 29, 2010 (Closed 35 days) |
PROJECT COMPLETE
 
Before After
|
|
Route: E
Bridge location: Big Muddy Creek
Work to be done: Bridge replacement
Originally built: 1952
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 7, 2010
Construction completed: Noveber 11, 2010 (Closed 44 days) |
PROJECT COMPLETE
 
Before After |
Route: D
Bridge location: Old Channel Shoal Creek
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 28, 2010
Construction completed: September 10, 2010 (Closed 43 days) |
PROJECT COMPLETE
 
Before After |
Route: K
Bridge location: Old Medicine Creek Channel
Work to be done: Bridge replacement
Originally built: 1938
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 27, 2010
Construction completed: September 13, 2010 (Closed 33 days) |
| |
|
PROJECT COMPLETE
 
Before After |
|
Route: P
Bridge location: Big Branch
Work to be done: Bridge replacement
Originally built: 1952
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 18, 2010
Construction completed: November 12, 2010 (Closed 45 days)
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 136 Hwy.
Bridge location: Wildcat Creek
Work to be done: Bridge replacement
Originally built: 1931
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: October 3, 2011 Construction completed: November 17, 2011 (Closed 43 days) Detour map: Click here for U.S. 136 Hwy. Detour
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: U.S. 71 Hwy.
Bridge location: White Cloud Branch
Work to be done: Bridge replacement
Originally built: 1933
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 29, 2012
Construction completed: June 29, 2012 (Closed 31 days)
Detour map: Click here for U.S. Hwy. 71 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route J
Bridge location: Sleek Creek
Work to be done: Bridge replacement
Originally built: 1939
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 27, 2010
Construction completed: November 2, 2010 (Closed 36 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 246
Bridge location: Honey Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 28, 2011
Construction completed: June 17, 2011 (Closed 81 days)
Detour map: Click here for MO 246 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 246
Bridge location: Brushy Creek
Work to be done: Bridge replacement
Originally built: 1947
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 1, 2011
Construction completed: September 2, 2011 (Closed 32 days)
Detour map: Click here for MO 246 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route A
Bridge location: Elkhorn Creek
Work to be done: Bridge redeck
Originally built: 1953
Closure date: June 5,2012
Construction completed: July 20, 2012 (Closed 47 days)
Detour map: Click here for Route A Detour |
| PROJECT COMPLETE |
|
|
 
Before After |
|
Route: Route JJ
Bridge location: West Fork 102 River
Work to be done: Bridge redeck
Originally built: 1955
Awarded on: March 4th
Award Amount: $314,107.11
Awarded to: A.M. Cohron & Sons, Inc.
Closure date: July 27, 2009
Completion date: September 14, 2009 (Closed 48 days) |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route VV
Bridge location: Long Branch
Work to be done: Bridge redeck
Originally built: 1956
Closure date: May 14, 2012
Completion date: September 14, 2009 (Closed 44 days)
Detour map: Click here for Route VV Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 246
Bridge location: Norvey Creek
Work to be done: Bridge replacement
Originally built: 1952
Awarded to: KTU Constructors (Design-Build Contract)
Closed date: March 14, 2011
Completion date: April 29, 2011 (Closed 47 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route NN
Bridge location: Honey Creek
Work done: Bridge redeck
Originally built: 1955
Award amount: $238,560.34
Awarded to: Loch Sand and Construction Co.
Closure date: March 17, 2009
Construction completed: April 29, 2009 (Closed 43 Days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route NN
Bridge location: Brushy Creek
Work to be done: Bridge redeck
Originally built: 1955
Award amount: $194,738.84
Awarded to: Loch Sand and Construction Co.
Closure date: April 1, 2009
Construction completed: May 12, 2009 (Closed 42 Days)
|
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: Route PP
Bridge location: Huff Creek
Work to be done: Bridge redeck
Originally built: 1961
Awarded on: September 2, 2009
Award amount: $255,609.75
Awarded to: Boone Construction Co.
Closure date: October 13, 2009 Construction completed: November 17, 2009 (Closed 35 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route PP
Bridge location: Maupin Creek
Work to be done: Bridge redeck
Originally built: 1961
Awarded on: September 2, 2009
Award amount: $259,039.75
Awarded to: Boone Construction Co.
Closure date: March 8, 2010 Construction completed: April 12, 2010 (Closed 37 days)
|
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route A
Bridge location: Jenkins Creek
Work to be done: Bridge replacement
Originally built: 1930
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: February 28, 2011
Construction completed: April 22, 2011 (Closed 53 days)
Detour map: Click here for Route A Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 113
Bridge location: Nodaway River
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: July 5, 2011
Construction completed: September 22, 2011 (Closed 77 days)
Detour map: Click here for MO 113 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After
|
|
Route: MO 113
Bridge location: Nodaway River South Overflow
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: May 10, 2011
Construction completed: July 5, 2011 (Closed 56 days)
Detour map: Click here for MO 113 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 113
Bridge location: Nodaway River North Overflow
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: March 21, 2011
Construction completed: May 10, 2011 (Closed 49 days)
Detour map: Click here for MO 113 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 113
Bridge location: Cayhoga Creek
Work to be done: Bridge replacement
Originally built: 1950
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: June 2, 2011
Construction completed: July 1, 2011 (Closed 28 days)
Detour map: Click here for MO 113 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 113
Bridge location: Bowman Branch
Work to be done: Bridge replacement
Originally built: 1934
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: July 6, 2011
Construction completed: August 8, 2011 (Closed 32 days)
Detour map: Click here for MO 113 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: MO 113
Bridge location: Sand Creek
Work to be done: Bridge replacement
Originally built: 1934
Awarded to: KTU Constructors (Design-Build Contract)
Closed for construction: April 2, 2012
Construction completed: May 7, 2012 (Closed 36 days)
Detour map: Click here for MO 113 Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route F
Bridge location: Mozingo Creek
Work to be done: Bridge replacement
Originally built: 1936
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 30, 2010
Construction completed: October 5, 2010 (Closed 35 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route M
Bridge location: Shankton Branch
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 20, 2010
Construction completed: October 23, 2010 (Closed 42 days)
|
PROJECT COMPLETE
 
Before After |
|
Route: Route 139
Bridge location: Barber Creek
Work to be done: Bridge replacement
Originally built: 1933
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 19, 2010
Construction completed: October 2, 2010 (Closed 45 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route EE
Bridge location: West Locust Creek
Work to be done: Bridge deck replacement
Originally built: 1960
Closure date: March 8, 2010
Construction completed: April 21, 2010 (Closed 44 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route 136
Bridge location: East Locust Creek
Work to be done: Bridge replacement
Originally built: 1931
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 2, 2010
Construction completed: September 23, 2010 (Closed 56 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route 5
Bridge location: Blackbird Creek
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 9 , 2010
Construction completed: July 23, 2010 (Closed 42 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route 139
Bridge location: Unnamed Stream
Work to be done: Bridge replacement
Originally built: 1933
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: November 3, 2010
Construction completed: November 30, 2010 (Closed 35 days) |
PROJECT COMPLETE
 
Before After
|
|
Route: Route 6
Bridge location: Muddy Creek
Work to be done: Bridge replacement
Originally built: 1932
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 18, 2010
Construction completed: November 23, 2010 (Closed 31 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route 5
Bridge location: Elmwood Creek
Work to be done: Bridge replacement
Originally built: 1929
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 29, 2010
Construction completed: October 27, 2010 (Closed 31 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route 129
Bridge location: Little Yellow Creek
Work to be done: Bridge replacement
Originally built: 1931
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 29, 2010
Construction completed: November 2, 2010 (Closed 36 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route C
Bridge location: Little Yellow Creek
Work to be done: Bridge replacement
Originally built: 1952
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: June 6, 2011
Construction completed: July 12, 2011 (Closed 35 days)
|
PROJECT COMPLETE
 
Before After |
|
Route: Route O
Bridge location: Long Branch
Work to be done: Bridge replacement
Originally built: 1954
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: October 11, 2010
Construction completed: December 4, 2010 (Closed 42 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route H
Bridge location: Mussel Creek
Work to be done: Bridge replacement
Originally built: 1955
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 11, 2011
Construction completed: August 29, 2011 (Closed 48 days)
|
PROJECT COMPLETE
 
Before After |
|
Route: Route N
Bridge location: Yellow Creek
Work to be done: Bridge replacement
Originally built: 1923
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: May 24, 2010
Construction completed: July 10, 2010 (Closed 47 days) |
PROJECT COMPLETE
 
Before After |
|
Route: Route PP
Bridge location: Middle Fork Grand River
Work to be done: Bridge replacement
Originally built: 1958
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: August 1, 2011
Construction completed: September 23, 2011 (Closed 52 days)
Detour map: Click here for Route PP Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route C
Bridge location: Little Rock Creek
Work to be done: Bridge replacement
Originally built: 1951
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: September 19, 2011
Construction completed: November 1, 2011 (Closed 42 days)
Detour map: Click here for Route C Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route W
Bridge location: Bear Creek
Work to be done: Bridge replacement
Originally built: 1937
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: March 21, 2011
Construction completed: April 27, 2011 (Closed 37 days)
Detour map: Click here for Route W Detour |
| |
|
|
PROJECT COMPLETE

Before |
|
Route: Route T
Bridge location: Lotts Creek
Work to be done: Bridge replacement
Originally built: 1934
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: July 9, 2012
Construction completed: August 20, 2012 (Closed 37 days)
Detour map: Click here for Route T Detour |
| |
|
|
PROJECT COMPLETE
 
Before After |
|
Route: Route W
Bridge location: Oxcart Creek
Work to be done: Bridge replacement
Originally built: 1948
Awarded to: KTU Constructors (Design-Build Contract)
Closure date: April 27, 2011
Construction completed: June 6, 2011 Detour map: Click here for Route W Detour |
|
| |
| |
| |
`
|
|
|
 |
|
 |
|
 |
| Your Local MoDOT |
| Get your local district information. |
 |
|
|
|
|
|
|