     The Safe & Sound Bridge Program in Northwest Missouri improved 190 bridges.  The program began in 2008 and was completed in 2012 ahead of schedule. In just slightly more than 3-and-a-half years a project that was expected to take more than five years has been completed. And as a result, Missourians in every county of the state are driving across new and improved bridges that will serve their needs for many years to come.

 

              The $685 million Safe & Sound Bridge Improvement Program drew to a close on November 8 with a ribbon-cutting ceremony on the Route 11 bridge over the BNSF Railroad in Chariton County. At the event, Missouri Highways and Transportation Commission Chairman Rudy Farber said, “

"This was a fabulous program - the biggest bridge program in Missouri history. It’s really hard to imagine – 802 new or improved bridges in just 3-1/2 years.”


We want to hear your questions or comments about the Safe & Sound program. Please click on the button and fill out the

comment form.

Safe&Sound Comments


 

Safe & Sound

 

 

190 Bridges In

Northwest Missouri

Now Completed

 

 

 

 

Andrew County                                    Andrew County Bridge Map - Click here

PROJECT COMPLETE

U.S. 59 Hwy. Over IS 29U.S. 59 Hwy. / Bus. 71

Before                     After

PROJECT COMPLETE

Bus. 71 Hwy.U.S. 59 Hwy. / Bus. 71 soutbound

Before                     After

 

Route:  U.S. 59 Hwy. / Bus. 71 Hwy. (northbound)

Bridge location:  at Interstate 29

Work to be done: Bridge redeck

Originally built:  1962

Awarded on:  May 11, 2010

Award amount:  $1,816.999.30 (Includes work on north & southbound bridges)

Awarded to:  Loch Sand & Construction, Co.

Construction begins:  June 14, 2010

Closure date:  July 21, 2010

Construction complete:  November 2, 2010  

 

Route:  U.S. 59 Hwy. / Bus. 71 Hwy. (southbound)

Bridge location:  at Interstate 29

Work to be done: Bridge redeck

Originally built: 1962

Awarded on:  May 11, 2010

Award amount:  $1,816.999.30 (Includes work on north & southbound bridges)

Awarded to:  Loch Sand & Construction, Co.

Construction begins:  June 14, 2010

Closure date:  September 8, 2010

Construction complete:  November 2, 2010  

     

PROJECT COMPLETE

US 169 over Niagara CreekNiagara Creek

Before                    After

 

Route: U.S. 169 Hwy.

Bridge location:  Niagara Creek

Work to be done: Bridge replacement

Originally built: 1928

Awarded to:  KTU Constructors (Design-Build Contract)

Closed for construction: July 23, 2012 

Construction complete:  August 11, 2012 (Closed 19 days)

Detour mapAndrew Route 169 Detour

     

PROJECT COMPLETE

MO 48 over Platte River OverflowMo 48

Before                  After

 

Route: MO 48

Bridge location:  MO 48 at Platte River Overflow

Work to be done: Bridge replacement

Originally built: 1932

Awarded to:  KTU Constructors (Design-Build Contract)

Closed for construction:  May 16, 2011

Construction completed:  June 22, 2011 (Closed 37 days)                          Detour mapClick here for MO 48 Detour

     

PROJECT COMPLETE

Route H Pedlar CreekPedlar Creek Bridge

Before                     After

 

Route: Route H

Bridge location:  Pedlar Creek

Work to be done: Bridge redeck

Originally built: 1954

Awarded on:  December 5, 2008

Award amount:  $208,455.90

Awarded to:  Boone Construction Company

Closure date:  April 6, 2009

Construction completed:  May 20, 2009 (Closed 44 days)

     

PROJECT COMPLETE

Dillon CreekDillon Creek

Before                   After

 

Route: Route DD

Bridge location:  Dillon Creek

Work to be done:  Bridge replacement

Originally built:  1958

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  June 21, 2010

Construction completed:  August 24, 2010 (Closed 65 days)

     

PROJECT COMPLETE

Route Y Owl CreekRoute Y Owl Creek

Before                 After

 

Route: Route Y

Bridge location:  Owl Creek

Work to be done: Bridge replacement

Originally built: 1954

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  May 16, 2011

Construction completed:  June 28, 2011 (Closed 44 days)                                Detour mapClick here for Route Y Detour

     

PROJECT COMPLETERoute H over Arapahoe Creek

Route H Arapahoe

Before                 After

 

Route: Route H

Bridge location:  Arapahoe Creek

Work to be done:  Bridge replacement

Originally built:  1954

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  September 7, 2010

Construction completed:  October 28, 2010 (Closed 51 days)

 

     

PROJECT COMPLETE

Route A drainage ditch Route A

Before                 After

 

Route: Route A

Bridge location:  drainage ditch

Work to be done: Bridge replacement

Originally built: 1930

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  July 6, 2011

Construction completed:  August 15, 2011 (Closed 39 days)

Detour mapClick here for Route A Detour

 

Atchison County                             Atchison County Bridge Map - Click here

PROJECT COMPLETE

U.S. 59 Hwy. over Tarkio Creek59 Hwy.

Before                 After

 

Route: U.S. 59 Hwy.

Bridge location:  at Tarkio River

Work to be done:  Bridge replacement

Originally built: 1936

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date: January 30, 2012                                                             Construction completed:  April 16, 2012  (Closed 77 days )                         Detour Map:  Click here for U.S. 59 Hwy. Detour                                                             

     

PROJECT COMPLETE

US 136 Cow Creek BridgeCow Creek

Before                 After

 

Route: U.S. 136 Hwy.

Bridge location: Cow Creek

Work to be done: Bridge replacement  

Originally built: 1946

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  May 21, 2012 

Construction completed:  July 3, 2012 (Closed 43 days)

Detour Map:Click here for US 136 Hwy. Detour

PROJECT COMPLETE

MO 46 - over Hickory CreekRoute 46

Before                 After

 

Route: MO 46

Bridge location: Hickory Creek

Work to be done: Bridge replacement

Originally built: 1936

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  May 14, 2012 

Construction completed:  June 15, 2012  (Closed 32 days)    

Detour Map: Click here for MO 46 Detour

     

PROJECT COMPLETE

MO 46 - Little Tarkio Drainage DitchLittle Tarkio Drainage Ditch

Before                 After

 

Route: MO 46

Bridge location: Little Tarkio Drainage Ditch

Work to be done:  Bridge replacement  

Originally built: 1935

Awarded to:  KTU Constructors (Design-Build Contract)

Closed for construction:  June 3, 2011

Construction completed:  August 11, 2011 (Closed 65 days)

Detour Map: Click here for MO 46 Detour

     

PROJECT COMPLETE US 275 - Kings BridgeBridge

Before                     After

 

Route:  U.S. 275 Hwy.

Bridge location:  Kings Bridge

Work to be done:  Bridge redeck

Originally built: 1951

Awarded on:  March 4th

Award amount:  $255,037.80

Awarded to:  A.M. Cohron & Sons, Inc. 

Closure date:  June 1, 2009

Construction completed:  July 27, 2009 (Closed 53 days)

     

PROJECT COMPLETE

Route C - Mid Tarkio CreekRoute C Mid Tarkio Cr.

Before                     After

 

Route: Route C

Bridge location: Mid Tarkio Creek

Work to be done: Bridge replacement

Originally built: 1938

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:   May 31, 2011

Construction completed: August 3, 2011 (Closed 63 days)

Detour Map:  Click here for Route C Detour

     

PROJECT COMPLETE

Route C - Tarkio RiverTarkio River

Before                 After

 

Route: Route C

Bridge location:  Tarkio River

Work to be done: Bridge replacement

Originally built: 1938

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  August 4, 2011 

Construction completed:  October 18, 2011 (Closed 74 days)

Detour Map: Click here for Route C Detour

     

PROJECT COMPLETE

Route M Long Branch Creek BridgeBridge

Before                     After

 

Route: Route M

Bridge location: Long Branch Creek

Work to be done:  Bridge redeck

Originally built: 1961 

Awarded on: March 4th 

Award Amount:  $216,274.78

Awarded to:  A.M. Cohron & Sons, Inc.

Closure Date:  April 7, 2009 

Construction completed:  May 28, 2009 (Closed 50 days)

     

PROJECT COMPLETE

Route V - Main drainage ditchDrainage Ditch #6

Before                 After

 

Route: Route V

Bridge location:  Main Drainage Ditch #6

Work to be done:  Bridge replacement  

Originally built: 1954

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  March 14, 2011

Construction completed:  May 23, 2011 (Closed 71 days)

Detour Map: Click here for Route V Detour

     

PROJECT COMPLETE

Route B at Halls BranchHalls Branch Bridge

Before                 After

 

Route: Route B

Bridge location: Halls Branch

Work to be done: Bridge replacement

Originally built: 1930

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date: May 3, 2011

Construction completed:  June 17, 2011 (Closed 46 days)

Detour Map: Click here for Route B Detour

     

PROJECT COMPLETE

MO 46 - East Fork Hickory CreekEast Fork Hickory Cr

Before                 After

 

Route: MO 46

Bridge location: East Fork Hickory Creek

Work to be done: Bridge replacement

Originally built: 1936

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  August 15, 2011 

Construction completed:  September 14, 2011 (Closed 29 days)

Detour Map: Click here for MO 46 Detour

     

PROJECT COMPLETE

MO 111 - over Turkey CreekTurkey Creek

Before                 After

 

Route: MO 111

Bridge location: Turkey Creek

Work to be done: Bridge replacement

Originally built: 1936

Awarded to:  KTU Constructors (Design-Build Contract)

Closed for construction:  November 7, 2011

Construction completed: December 9, 2011 (Closed 32 days)

Detour Map: Click here for MO 111 Detour

     

PROJECT COMPLETE

MO 111-Drainage DitchDrainage Ditch

Before                 After

 

Route: MO 111

Bridge location: Drainage Ditch

Work to be done: Bridge replacement

Originally built: 1936

Awarded to:  KTU Constructors (Design-Build Contract)

Closed for construction:  October 31, 2011

Construction completed: December 9, 2011 (Closed 39 days)

Detour Map: Click here for MO 111 Detour

     

PROJECT COMPLETE

Route B - over Rock CreekRock Creek

Before                 After

 

Route: Route B

Bridge location: Rock Creek

Work to be done:  Bridge replacement

Originally built: 1948

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  September 12, 2011

Construction completed: October 25, 2011 (Closed 43 days)  

Detour Map: Click here for Route B Detour

 

Buchanan County                             Buchanan County Bridge Map - Click here

PROJECT COMPLETE

Route O at Interstate 29Bridge

Before                     After

 

Route: Route O

Bridge location: Interstate 29

Work to be done:  Bridge redeck

Originally built: 1958

Community briefing held: Tuesday, February 24, 2009

Awarded on:  April 1, 2009

Award amount:  $401,870.00

Awarded to:  Clarkson Construction Company

Closure date:  September 8, 2009

Construction completed:  October 9, 2009 (Closed 30 days)

     

PROJECT COMPLETE
U.S. 169 at Interstate 29US 169 Bridge

Before                     After

 

Route: U.S. 169 Hwy.

Bridge location: Interstate 29

Work to be done:  Bridge redeck

Originally built: 1962

Community briefing held: Thursday, February 26, 2009

Awarded on:  April 1, 2009

Award amount:  $1,067,858.00

Awarded to:  Clarkson Construction Company

Closure date:  July 10, 2009

Construction completed:  August 25, 2009 (Closed 48 days)

     

PROJECT COMPLETE

Route CC at South Fork of Bee Creekbridge

Before                     After

 

Route: Route CC

Bridge location: South Fork of Bee Creek

Work to be done:  Bridge redeck

Originally built: 1969

Community briefing held: Tuesday, February 24, 2009

Awarded on:  April 1, 2009

Award amount:  $326,088.40

Awarded to:  Clarkson Construction Company

Closure date:  June 8, 2009

Construction completed:  July 18, 2009 (Closed 41 days)

     

PROJECT COMPLETE

US 59 at CloverdaleCloverdale Bridge

Before                 After

 

Route: U.S. 59 Hwy.

Bridge location: Cloverdale Ditch

Work to be done:  Bridge replacement

Originally built: 1941

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date: March 19, 2012 

Construction completed: May 3, 2012 (Closed 45 days)

Detour Map:  Click here for US 59 Hwy. Detour

     

PROJECT COMPLETE

US 59 at Gay BranchGay Branch

Before                  After

 

Route: U.S. 59 Hwy.

Bridge location: Gay Branch

Work to be done:  Bridge replacement

Originally built: 1920

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date: March 19, 2012

Construction completed: May 3, 2012 (Closed 45 days)

Detour Map: Click here for US 59 Hwy. Detour

     

PROJECT COMPLETE

MO 116 Lost CreekLost

Before                 After

 

Route: MO 116

Bridge location: Lost Creek

Work to be done:  Bridge replacement

Originally built: 1950

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date  June 18, 2012

Construction completed: July 20, 2012 (Closed 33 days)

Detour Map:  Click here for MO 116 Detour

     

PROJECT COMPLETE

Route M at Sugar CreekSugar Creek

Before                  After

 

Route: Route M

Bridge location: Sugar Creek

Work to be done:  Bridge replacement  

Originally built: 1956

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date: June 25, 2012 

Construction completed: August 11, 2012 (Closed 47 days)

Detour Map: Click here for Route M Detour

     

PROJECT COMPLETE

Route DD at Malden Creek

Before   

 

Route: Route DD

Bridge location: Malden Creek

Work to be done: Bridge replacement

Originally built: 1954

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  July 23, 2012

Construction completed: August 25, 2012 (Closed 32 days)

Detour Map: Click here for Route DD Detour

     

PROJECT COMPLETE

MO 116 at Bee CreekBee Creek

Before                 After

 

Route: MO 116

Bridge location: Bee Creek

Work to be done: Bridge replacement

Originally built: 1933

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date: March 19, 2012

Construction completed:  April 26, 2012 (Closed 38 days)  

Detour Map: Click here for MO 116 Detour

     

PROJECT COMPLETE

MO 116 at Little Bee CreekLittle Bee Creek

Before                 After

 

Route: MO 116

Bridge location: Little Bee Creek

Work to be done:  Bridge replacement  

Originally built: 1933

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  May 14, 2012 

Construction completed:  June 13, 2012 (Closed 30 days)  

Detour Map: Click here for MO 116 Detour

     

PROJECT COMPLETE

Route P at Third ForkRoute P

Before                 After

 

Route: Route P

Bridge location: Third Fork of Platte River

Work to be done:  Bridge replacement

Originally built: 1934

Awarded to:  KTU Constructors (Design-Build Contract)

Closed for construction:  March 12, 2012 

Construction completed:  April 26, 2012 (Closed 44 days)

Detour Map: Click here for Route P Detour

     

PROJECT COMPLETE

Puckett Sl;uPuckett Slu

Before                     After

 

Route: Route KK

Bridge location: Puckett Slu

Work to be done:  Bridge replacement

Originally built: 1936

Awarded on:  May, 2009

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  October 19, 2009

Construction completed:  November 10, 2009 (Closed 22 days)

     

PROJECT COMPLETE

Route H at WolfpenWolfpen Creek

Before                 After

 

Route: Route H

Bridge location: Wolfpen Creek

Work to be done:  Bridge replacement

Originally built: 1948

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  October 3, 2011 

Construction completed:  November 3, 2011 (Closed 30 days)

Detour Map: Click here for Route H Detour

 

Caldwell County                                Caldwell County Bridge Map - Click here

     

PROJECT COMPLETE

US 36 UP RRUS 36 Hwy.

Before                 After

 

Route: US 36 Hwy. (westbound)

Bridge location: Union Pacific Railroad Bridge

Work to be done:  Bridge replacement

Originally built: 1958

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  April 30, 2012

Construction completed:  June 23, 2012 (Closed 54 days)

Detour map: Click here for U.S. 36 Hwy. Detour

     

PROJECT COMPLETE

MO 116 - N. Mud Creek116 N. Mud Creek

Before                     After

 

Route: MO 116

Bridge location: N. Mud Creek

Work to be done: Bridge redeck

Originally built: 1964

Awarded on:  September 2, 2009     

Award amount:  $267,963.00

Awarded to: Chester Bross Cons. Co./C.B. Equipment, Inc.

Closure date:  April 5, 2010     

Construction Completed:  May 20th 2010 (Closed 45 days)

     

PROJECT COMPLETE

Route A at Dead Oak CreekDead Oak Creek

Before                  After

 

 

Route: Route A

Bridge location: Dead Oak Creek

Work to be done: Bridge redeck 

Originally built: 1966                                                                                     Awarded on:  September 2, 2009     

Award amount:  $177,808.50

Awarded to: Chester Bross Cons. Co./C.B. Equipment, Inc.

Closure date: May 24, 2010

Construction Completed:  June 23, 2010 (Closed 29 days)

     

PROJECT COMPLETE

Route W at East Sheep CreekEast Sheep Creek

Before                 After

 

Route: Route W

Bridge location: East Sheep Creek

Work to be done:  Bridge replacement  

Originally built: 1923

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  May 7, 2012

Construction Completed:  June 6, 2012 (Closed 30 days)

Detour map: Click here for Route W Detour

 
     

PROJECT COMPLETE

Route N at Mud CreekRoute N Mud Creek

Before                  After

 

Route: Route N

Bridge location: Mud Creek  

Work to be done: Bridge redeck 

Originally built: 1958                                                                                     Awarded on:  September 2, 2009     

Award amount:  $236,095.00

Awarded to: Chester Bross Cons. Co./C.B. Equipment, Inc.

Closure date:  April 19, 2010

Construction completed:  June 4, 2010  (Closed 47 days)  

     

PROJECT COMPLETE

Route U at Otter CreekCaldwell Route U Otter Creek

Before                 After

 

Route: Route U

Bridge location: Otter Creek  

Work to be done:  Bridge redeck

Originally built: 1960

Awarded to:  Widel Inc.  

Closure date:  April 25, 2011

Construction completed: June 29, 2011 (Closed 65 days)

Detour map:  Click here for Route U Detour

 
     

PROJECT COMPLETE

Route D at Goose CreekGoose Creek

Before                 After

 

Route: Route D

Bridge location: Goose Creek  

Work to be done:  Bridge replacement

Originally built: 1954

Awarded to:  KTU Constructors (Design-Build Contract)                               Closure date:  April 23, 2012 

Construction completed: May 30, 2012 (Closed 38 days)

Detour map:  Click here for Route D Detour

     

PROJECT COMPLETE

Route H at Plum CreekRoute HH Plum Creek

Before                 After

 

Route: Route HH

Bridge location: Plum Creek

Work to be done: Bridge redeck

Originally built: 1965

Awarded to:  Widel Inc.

Closure date: June 1, 2011

Construction completed:  July 15, 2011  (Closed 44 days)

Detour map: Click here for Route HH Detour

 
     

PROJECT COMPLETE

Route A at Panther CreekPanther Creek

Before                 After

 

Route: Route A

Bridge location: Panther Creek  

Work to be done:  Bridge replacement

Originally built: 1947

Awarded to:  KTU Constructors (Design-Build Contract)                                

Closure date: April 2, 2012

Construction completed:  May 10, 2012  (Closed 39 days)

Detour map:  Click here for Route A Detour

 

 Carroll County                                 Carroll County Bridge Map - Click here

PROJECT COMPLETE

Fish Pond CreekFish Pond Creek

Before                    After

 

Route: Route E

Bridge location: Fish Pond Creek  

Work to be done:  Bridge replacement

Originally built: 1946

Awarded to:  KTU Constructors (Design-Build Contract)                                 Closure date:  June 25, 2010

Construction completed:  July 24, 2010 (Closed 37 days)  

     

PROJECT COMPLETE

McCroskie CreekRoute E McCroskie

Before                    After

 

Route: Route E

Bridge location: McCroskie Creek

Work to be done:  Bridge replacement

Originally built: 1946

Awarded to:  KTU Constructors (Design-Build Contract)
Closure date: 
April 25, 2010

Construction completed:  July 3, 2010 (Closed 84 days)  

     

PROJECT COMPLETE

Camp CreekRoute B Camp Creek

Before                    After

 

Route: Route B

Bridge location: Camp Creek

Work to be done:  Bridge replacement

Originally built: 1951

Awarded to:  KTU Constructors (Design-Build Contract)
Closure date: 
April 25, 2010

Construction completed:  May 24, 2010 (Closed 36 days)

 

     

PROJECT COMPLETE

Camp CreekCamp Creek

Before                     After

 

 

Route: Route B

Bridge location: Camp Creek

Work to be done:  Bridge replacement

Originally built: 1930

Awarded to:  KTU Constructors (Design-Build Contract)
Closure date: 
May 19, 2010

Construction completed:  June 30, 2010 (Closed 35 days)

     

PROJECT COMPLETE

McCroskie CreekRoute O McCroskie Creek

Before                     After

 

Route: Route OO

Bridge location: McCroskie Creek

Work to be done:  Bridge replacement

Originally built: 1956

Awarded to:  KTU Constructors (Design-Build Contract)
Closure date: 
July 19, 2010

Construction completed:  August 27, 2010 (Closed 37 days)

     

PROJECT COMPLETE

Big CreekRoute M Big Creek

Before                     After

 

Route: Route M

Bridge location: Big Creek

Work to be done:  Bridge replacement

Originally built: 1958

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  June 28, 2010

Construction completed:  August 20, 2010 (Closed 53 days)

 

 

     

PROJECT COMPLETE

Bridge CreekRoute M Big Creek

Before                     After

 

Route: Route M

Bridge location: Bridge Creek

Work to be done:  Bridge deck replacement

Originally built: 1958

Awarded to:  Widel, Inc.

Closure date:  September 2, 2009

Construction completed:  October 30, 2009  (Closed 59 days)

 

     

PROJECT COMPLETE

Wolf CreekWolf Creek

Before                     After

 

Route: Route M

Bridge location: Wolf Creek

Work to be done:  Bridge replacement

Originally built: 1958

Awarded to:  KTU Constructors (Design-Build Contract)
Closure date: 
April 4, 2011

Construction completed:  May 3, 2011  (Closed 36 days)

 

     

PROJECT COMPLETE

Burr Oak CreekRoute W Burr Creek

Before                     After

 

Route: Route W

Bridge location: Burr Oak Creek

Work to be done:  Bridge replacement

Originally built: 1955

Awarded to:  KTU Constructors (Design-Build Contract)
Closure date: 
May 14, 2011

Construction completed:  July 1, 2010  (Closed 46 days)

PROJECT COMPLETE

Big Creek OverflowRoute 139 Big Creek Overflow

Before                    After

 

Route: Route 139

Bridge location: Big Creek Overflow

Work to be done:  Bridge replacement

Originally built: 1932

Awarded to:  KTU Constructors (Design-Build Contract)
Closure date: 
August 18, 2010

Construction completed:  November 24, 2010  (Closed 114 days)

     

PROJECT COMPLETE

Big Creek Drainage DitchRoute 139 Big Creek Drainage Ditch

Before                    After

 

Route: Route 139

Bridge location: Big Creek Drainage Ditch

Work to be done:  Bridge replacement

Originally built: 1932

Awarded to:  KTU Constructors (Design-Build Contract)
Closure date: 
August 18, 2010

Construction completed:  November 24, 2010  (Closed 114 days)

     

PROJECT COMPLETE

Big CreekRoute 139 Big Creek

Before                     After

 

Route: Route 139

Bridge location: Big Creek

Work to be done:  Bridge replacement

Originally built: 1932

Awarded to:  KTU Constructors (Design-Build Contract)
Closure date: 
August 18, 2010

Construction completed:  November 24, 2010  (Closed 114 days)

     

PROJECT COMPLETE

Mound CreekRoute J Mound Creek

Before                    After

 

Route: Route J

Bridge location: Mound Creek

Work to be done:  Bridge replacement

Originally built: 1934

Awarded to:  KTU Constructors (Design-Build Contract)
Closure date: 
April 12, 2010

Construction completed:  May 21, 2010  (Closed 43 days)

 Chariton County                              Chariton County Bridge Map - Click here

PROJECT COMPLETE

BNSF

  

 

Route: MO 11

Bridge location: BNSF

Work to be done:  Bridge replacement

Originally built: 1936

Awarded to:  KTU Constructors (Design-Build Contract)                                 Closure date:  September 4, 2012

Construction completed:  November 9, 2012  (Closed 60 days)

 

PROJECT COMPLETE

Puzzle CreekRoute P Puzzle Creek

Before                     After

 

Route: Route P

Bridge location: Puzzle Creek

Work to be done:  Bridge replacement

Originally built: 1948

Awarded to:  KTU Constructors (Design-Build Contract)                                 Closure date:  March 7, 2011

Construction completed:  April 14, 2011  (Closed 53 days)

 

Clinton County                                 Clinton County Bridge Map - Click here

PROJECT COMPLETE

Route PP at New Hope CreekNew Hope Creek

Before                 After

 

Route: Route PP

Bridge location: New Hope Creek

Work to be done:  Bridge replacement  

Originally built: 1959 

Awarded to:  KTU Constructors (Design-Build Contract)    

Closure date:  September 12, 2011                                                                       Construction completed:  October 18, 2011 (Closed 36 days)                              Detour Map:  Click here for Route PP Detour

     

PROJECT COMPLETE
Route K at Castile CreekClinton Route K

Before                 After

 

Route: Route K

Bridge location: Castile Creek

Work to be done:  Bridge redeck

Originally built: 1960

Awarded to:  Widel Inc.

Closure date: February 28, 2011

Construction complete:  April 29, 2011 (Closed 59 days)

Detour Map: Click here for Route K Detour

     

PROJECT COMPLETE

Route V at Interstate 35Clinton County Route V

Before                 After

 

Route:  Route V

Bridge location: Interstate 35  

Work to be done:  Bridge redeck

Originally built: 1964

Awarded to: Widel Inc.  

Closure date:  March 14, 2011 

Construction complete:  May 6, 2011 (Closed 52 days)

Detour Map: Click here for Route V Detour

     

PROJECT COMPLETE

MO 121 at Deer CreekDeer Creek

Before                 After

 

Route: MO 121

Bridge location: Deer Creek  

Work to be done:  Bridge replacement

Originally built: 1935

Awarded to:  KTU Constructors (Design-Build Contract)    

Closure date: October 10, 2011

Construction complete:  November 10, 2011 (Closed 30 days)

Detour Map: Click here for MO 121 Detour

     

PROJECT COMPLETE

Route NN at McGuire CreekMcGuire Creek

Before                 After

 

Route: Route NN

Bridge location: McGuire Creek

Work to be done: Bridge replacement  

Originally built: 1947

Awarded to:  KTU Constructors (Design-Build Contract)    

Closure date: May 7, 2012  

Construction complete: June 8, 2012 (Closed 33 days)

Detour Map: Click here for Route NN Detour

 

Daviess County                               Daviess County Bridge Map - Click here

PROJECT COMPLETE

Route RA over E. Brushy Creek Daviess - Route RA Bridge

Before                     After

 

Route: Route RA

Bridge location: East Brushy Creek

Work to be done: Bridge redeck 

Originally built: 1972                                                            

Awarded on:  January 8, 2009     

Award amount:  $299,419.00

Awarded to:  Chester Bross Construction Company

Closure date:  May 26, 2009

Construction completed:  June 30, 2009 (Closed 35 days)

                                                                                                                         

     

PROJECT COMPLETE

MO 13 at Little Cypress CreekLittle Cypress Creek

Before                 After

 

Route: MO 13

Bridge location: Little Cypress Creek

Work to be done: Bridge replacement  

Originally built: 1937

Awarded to:  KTU Constructors (Design-Build Contract)    

Closed for construction:  October 31, 2011 

Construction completed: December 13, 2011 (Closed 43 days)

Detour Map: Click here for MO 13 Detour

     

PROJECT COMPLETE

Route T at Sampson CreekSampson Creek

Before                  After

 

Route: Route T

Bridge location: Sampson Creek  

Work to be done:  Bridge redeck

Originally built: 1957

Awarded to: Comanche Construction Inc.

Award amount:  $750,543.90

Closure date:  March 7, 2011

Construction completed: April 27, 2011 (Closed 50 days)  

     

PROJECT COMPLETE

Route CC at Dog CreekDog Creek

Before                 After

 

Route: Route CC

Bridge location: Dog Creek

Work to be done: Bridge bridge replacement  

Originally built: 1953

Awarded to:  KTU Constructors (Design-Build Contract)    

Closure date:  March 12, 2012 

Construction completed: April 24, 2012 (Closed 44 days)  

Detour Map: Click here for Route CC Detour

     

PROJECT COMPLETE

Route P at Pilot Grove CreekRoute P Pilot Grove Creek

Before                 After

 

Route: Route P

Bridge location: Pilot Grove Creek  

Work to be done:  Bridge replacement

Originally built: 1954

Awarded to:  KTU Constructors (Design-Build Contract)    

Closure date:  March 28, 2011

Construction completed:  May 10, 2011 (Closed 42 days)

Detour Map:  Click here for Route P Detour

     

PROJECT COMPLETE

Route P over Big Muddy CreekBig Muddy Creek

Before                 After

 

Route: Route P

Bridge location: Big Muddy Creek  

Work to be done:  Bridge replacement

Originally built: 1954

Awarded to:  KTU Constructors (Design-Build Contract)    

Closure date:  September 6, 2011 

Construction completed:  October 14, 2011 (Closed 38 days)

Detour Map:  Click here for Route P Detour

 
     

PROJECT COMPLETE

Route E at Grindstone CreekGrindstone Creek

Before                 After

 

Route: Route E

Bridge location: Grindstone Creek

Work to be done:  Bridge replacement

Originally built: 1954

Awarded to:  KTU Constructors (Design-Build Contract)    

Closure date: April 2, 2012 

Construction completed:  May 24, 2012 (Closed 53 days)

Detour Map:  Click here for Route E Detour

     

PROJECT COMPLETE

Route V at Muddy CreekMuddy Creek

Before                   After

 

Route: Route V

Bridge location: Muddy Creek

Work to be done:  Bridge redeck

Originally built: 1963

Awarded to:  Widel, Inc.

Closure date:  July 12, 2011

Construction completed:  September 6, 2011 (Closed 54 days)  

Detour Map:  Click here for Route V Detour

     

PROJECT COMPLETE

Route Z Drainage ditchDrainage Citch

Before                 After

 

Route: Route Z

Bridge location: Drainage ditch

Work to be done: Bridge redeck

Originally built: 1961

Awarded to:  Widel, Inc.

Closure date:  June 28, 2011

Construction completed:  August 23, 2011 (Closed 55 days)

Detour Map:  Click here for Route Z Detour

     

PROJECT COMPLETE

Route HH at Marrowbone CreekMarrowbone Creek

Before                 After

 

Route: Route HH

Bridge location: Marrowbone Creek

Work to be done: Bridge redeck

Originally built: 1962

Awarded to:  Widel, Inc.

Closure date:  August 23, 2011

Construction completed:  October 20, 2011 (Closed 57 days)

Detour Map:  Click here for Route HH Detour

 
     

PROJECT COMPLETE

Route J at Dog CreekDog Creek

Before                 After

 

Route: Route J

Bridge location: Dog Creek

Work to be done:  Bridge replacement

Originally built: 1931

Awarded to:  KTU Constructors (Design-Build Contract)    

Closure date:  May 29, 2012

Construction completed:  July 2, 2012 (Closed 34 days)

Detour Map:  Click here for Route J Detour

 
     

PROJECT COMPLETE

Route K at East CreekRoute K East Creek

Before                 After

 

Route: Route K

Bridge location: East Creek

Work to be done:  Bridge replacement

Originally built: 1934

Awarded to:  KTU Constructors (Design-Build Contract)    

Closure date:  May 16, 2011

Construction completed:  June 9, 2011 (Closed 23 days)

Detour Map:  Click here for Route K Detour

     

PROJECT COMPLETE

Route K at PIlot Grove CreekRoute P PIlot Grove Creek

Before                 After

 

Route: Route K

Bridge location: Pilot Grove Creek

Work to be done:  Bridge replacement

Originally built: 1934

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  June 6, 2011

Construction completed:  July 1, 2011 (Closed 25 days)

Detour Map:  Click here for Route K Detour

     

PROJECT COMPLETE

Route J at Marrowbone CreekMarrowbone Creek

Before                 After

 

Route: Route J

Bridge location: Marrowbone Creek

Work to be done:  Bridge replacement

Originally built: 1935

Awarded to:  KTU Constructors (Design-Build Contract)    

Closure date:  June 18, 2012

Construction completed:  July 23, 2012 (Closed 36 days)

Detour Map:  Click here for Route J Detour

     

PROJECT COMPLETE

Route M at Lick Fork CreekLick Fork Creek

Before                 After

 

Route: Route M

Bridge location: Lick Fork Creek

Work to be done:  Bridge replacement

Originally built: 1947

Awarded to:  KTU Constructors (Design-Build Contract)

Closed for construction:  August 8, 2011

Construction completed:  September 19, 2011 (Closed 41 days)

Detour Map:  Click here for Route M Detour

 

 

DeKalb County                                Dekalb County Bridge Map - Click here      

PROJECT COMPLETE

MO 33 at Lost CreekMO 33 Bridge

Before                     After

 

 

Route: MO 33

Bridge location: Branch of Lost Creek (Red Horse Creek)  

Work to be done:  Bridge redeck

Originally built: 1959

Awarded on:  December 2, 2009     

Award amount:  $258,526.93

Awarded to:  Loch Sand & Construction Co.

Closure date:  March 22, 2010

Construction completed:  April 27, 2010 (Closed 36 days)

 

     

PROJECT COMPLETE

MO 33 at West Fork Lost CreekMO 33

Before                  After 

 

Route: MO 33

Bridge location: West Fork Lost Creek

Work to be done:   Bridge redeck

Originally built: 1959

Awarded on:  December 2, 2009     

Award amount:  $252,744.35

Awarded to:  Loch Sand & Construction Co.

Closure date:  April 27, 2010

Construction completed:  June 3, 2010 (Closed 37 days)

 

     

PROJECT COMPLETE

U.S. 36 Hwy. at Castile CreekCastile Creek

Before                 After 

 

Route: U.S. 36 Hwy. (westbound)

Bridge location: Castile Creek

Work to be done:  Bridge replacement

Originally built: 1923

Awarded to:  KTU Constructors (Design-Build Contract)                                  Closure date:  May 4, 2011

Construction completed:  June 16, 2011 (Closed 42 days)

Detour map:  Click here for U.S. 36 Hwy. Westbound Detour

PROJECT COMPLETE

U.S. 36 W at Castile CreekCastile eastbound

Before                 After 

 

Route: U.S. 36 Hwy. (eastbound)

Bridge location: Castile Creek

Work to be done:  Bridge redeck

Originally built: 1966                                                                                        Closed for construction:  July 18, 2011  

Construction completed:  September 9, 2011 (Closed 51 days)

Detour map:  Click here for U.S. 36 Hwy. Eastbound Detour

 

 

   

PROJECT COMPLETE

U.S. 36 Hwy. at Grindstone CreekGrindsstone Creek

Before                 After 

 

Route: U.S. 36 Hwy. (westbound)

Bridge location: Grindstone Creek  

Work to be done:  Bridge redeck

Originally built: 1966                                                                                        Closed for construction:  August 29, 2011 

Construction completed:  October 12, 2011 (Closed 43 days)

Detour map:  Click here for U.S. 36 Hwy. Westbound Detour

 

     

PROJECT COMPLETE

Route A at East Fork Lost CreekEast Fork Lost Creek

Before                 After

 

Route: Route A

Bridge location: East Fork Lost Creek  

Work to be done:  Bridge replacement

Originally built: 1947

Awarded to:  KTU Constructors (Design-Build Contract)                                    Closed for construction:  October 17, 2011 

Construction completed: December 6, 2011 (Closed 49 days)

Detour map: Click here for Route A Detour

     

PROJECT COMPLETE

Route E at North Fork Lost CreekNorth Fork Lost Creek

Before                     After

 

Route: Route E

Bridge location: North Fork Lost Creek

Work to be done:  Bridge redeck

Originally built: 1956 

Awarded on:  January 8, 2009

Award amount:  $227,405.00

Awarded to:  St. Joseph Fuel Oil & Mfg. Co.

Closure date: June 22, 2009

Construction completed:  August 6, 2009 (Closed 45 days)

     

PROJECT COMPLETE

Route V at 3rd Fork Platte RiverRoute V Third Fork Platte River

Before                     After

 

Route: Route V

Bridge location: Third Fork Platte River  

Work to be done:  Bridge redeck

Originally built: 1957 

Award amount:  $277,330.00

Awarded to:  St. Joseph Fuel Oil & Mfg. Co.

Closure date:  March 30, 2009

Construction completed:  May 14, 2009 (Closed 46 days)

     

PROJECT COMPLETE

Route F at Crooked CreekCrooked Creek

Before                 After

 

Route: Route F

Bridge location: Crooked Creek  

Work to be done:  Bridge redeck

Originally built: 1961                                                                                        Award amount:  $291,606.84                                                                        Awarded to:  Chester Bross Const.  Co. / C.B. Equipment Inc.                        Closure date:  August 29, 2011                                                               Construction completed:  October 21, 2011 (Closed 52 days)

Detour map: Click here for Route F Detour

     

PROJECT COMPLETE
Route C Grindstone CreekGrindstone Creek

Before                     After

 

Route: Route C

Bridge location: Grindstone Creek  

Work to be done:  Bridge redeck

Originally built: 1952
Awarded on:  January 8, 2009
Award amount:  $271,372.00

Awarded to:  St. Joseph Fuel Oil & Mfg. Co.

Closure date:  May 11, 2009

Construction completed:  June 25, 2009 (Closed 45 days)

     

PROJECT COMPLETE

Route H at Dry BranchDry Branch Creek

Before                 After

 

Route: Route H

Bridge location: Dry Branch  

Work to be done:  Bridge replacement  

Originally built: 1953

Awarded to:  KTU Constructors (Design-Build Contract)   

Closure date: September 26, 2011   

Construction completed:  October 20, 2011

Detour map:  Click here for Route H Detour

     

PROJECT COMPLETE

Route J at abondoned railroad bridgeRoute J Amity

Before                     After

 

Route: Route J

Bridge location: Abandoned Railroad Bridge  

Work to be done:  Bridge removal

Originally built: 1964

Awarded on:  May 11, 2010
Award amount:  $178,145.79

Awarded to:  Widel, Inc.  

Closure date: August 2, 2010

Construction completed:  September 14, 2010 (Closed 44 days)

 

     

PROJECT COMPLETE

Route E at Little 3rd Fork Platte RiverLittle Third Fork Platte

Before                 After

 

Route: Route E

Bridge location: Little Third Fork Platte

Work to be done:  Bridge replacement

Originally built: 1947

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  November 7, 2011

Construction completed:  December 14, 2011 (Closed 37 days)

Detour map:  Click here for Route E Detour

     

PROJECT COMPLETE

Route E at Lost CreekLost Creek

Before                  After

 

Route: Route E

Bridge location: Lost Creek

Work to be done:  Bridge replacement

Originally built: 1947

Awarded to:  KTU Constructors (Design-Build Contract)                                   Closure date:  May 14, 2012

Construction completed: June 21, 2012 (Closed 38 days)

Detour mapClick here for Route E Detour

     

PROJECT COMPLETE

Route E at East Fork Lost CreekEast Fork Lost Creek

Before                    After

 

Route: Route E

Bridge location: East Fork Lost Creek

Work to be done: Bridge replacement

Originally built: 1941

Awarded to:  KTU Constructors (Design-Build Contract)                             

Closed for construction:  June 11, 2012

Construction completed: July 18, 2012 (Closed 38 days)                           

Detour map: Click here for Route E Detour

 

 

Gentry County                                    Gentry County Bridge Map - Click here

PROJECT COMPLETE

U.S. 169 Hwy at Old Channel Island CreekUS 169 Hwy.

Before                 After

 

Route: U.S. 169 Hwy.

Bridge location: Old Channel Island Creek

Work to be done:  Bridge removal

Originally built: 1941

Closure date: April 3, 2012 

Construction completed: April 11, 2012 (Closed 9 days)

Detour Map:  Click here for US 169 Hwy. Detour

     

PROJECT COMPLETE

MO 85 at Thompson BridgeMO 85

Before                 After

 

Route: MO 85

Bridge location: Thompson Branch

Work to be done: Bridge redeck  

Originally built: 1925

Closure date: January 25, 2012 

Construction completed:  April 7, 2012 (Closed 73 days)

Detour Map:  Click here for MO 85 Detour

     

PROJECT COMPLETE

MO 85 Town BridgeTown Creek

Before                 After

 

Route: MO 85

Bridge location: Town Creek

Work to be done:  Bridge replacement

Originally built: 1925

Awarded to:  KTU Constructors (Design-Build Contract)                           Closure date:  May 31, 2011

Construction completed:  July 8, 2011 (Closed 37 days)        

Detour Map: Click here for MO 85 Detour

 

     

PROJECT COMPLETE

U.S. 136 Hwy. Town BridgeTown Branch

Before                 After

 

Route: U.S. 136 Hwy.

Bridge location: Town Branch

Work to be done:  Bridge replacement

Originally built: 1929

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  June 6, 2011 

Construction completed:  July 20, 2011 (Closed 44 days)                        Detour Map: Click here for U.S. 136 Hwy. Detour

 

     

PROJECT COMPLETE

U.S. 136 Hwy. at Moccasin CreekMoccasin

Before                 After

 

Route: U.S. 136 Hwy.

Bridge location: Moccasin Creek

Work to be done:  Bridge replacement

Originally built: 1929

Awarded to:  KTU Constructors (Design-Build Contract)

Closed for construction:  August 15, 2011 

Construction completed:  October 3, 2011 (Closed 48 days)

Detour Map: Click here for U.S. 136 Hwy. Detour

 

     

PROJECT COMPLETE

Route UU at Turkey CreekRoute UU Turkey Creek

Before                 After

 

Route: Route UU

Bridge location: Turkey Creek

Work to be done: Bridge replacement  

Originally built: 1958

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  September 7, 2010

Construction completed:  October 30, 2010 (Closed 53 days)

 

     

PROJECT COMPLETE

Route BB at Island CreekRoute BB Bridge

Before                     After

 

Route: Route BB

Bridge location: Island Creek

Work to be done: Bridge redeck 

Awarded on:  January 9, 2009

Award amount:  $230,416.00

Awarded to:  Chester Bross Construction Company

Closure date:  June 8, 2009

Construction completed:  July 10, 2009 (Closed 33 days)

     

PROJECT COMPLETE

Route O at West Fork Grand RiverRoute O West Fork

Before                 After

 

Route: Route O

Bridge location: West Fork Grand River  

Work to be done: Bridge replacement  

Originally built: 1960

Awarded to:  KTU Constructors (Design-Build Contract)                            Closure date:  February 9, 2011 

Construction completed:  May 11, 2011  (Closed 90 days)

Detour Map: Click here for Route O Detour

     

PROJECT COMPLETE Route A at Evona CreekRoute A Evona Creek

Before                 After

 

Route: Route A

Bridge location: Evona Creek

Work to be done:  Bridge replacement

Originally built: 1930

Awarded to:  KTU Constructors (Design-Build Contract)                             Closure date: October 11, 2010

Construction completed:  November 11, 2010 (Closed 30 days)

 

     

PROJECT COMPLETE

Route H at West Fork Grand RiverWest Fork Grand River

Before                 After

 

Route: Route H

Bridge location: West Fork Grand River  

Work to be done: Bridge replacement  

Originally built: 1947

Awarded to:  KTU Constructors (Design-Build Contract)           

Closed for construction:  August 15, 2011

Construction completed:  October 12, 2011 (Closed 57 days)

Detour Map:  Click here for Route H Detour

 

     

PROJECT COMPLETE

Route M at Island CreekGentry County Route M

Before                 After

 

Route: Route M

Bridge location: Island Creek  

Work to be done: Bridge replacement  

Originally built: 1948

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  March 14, 2011 

Construction completed:  May 4, 2011 (Closed 51 days)

Detour Map:  Click here for Route M Detour

 

 

 Grundy County                                 Grundy County Bridge Map - Click here

PROJECT COMPLETE

Hickory CreekRoute WW Hickory Creek

Before                     After

 

Route: Route WW

Bridge location:  Hickory Creek

Work to be done:  Bridge replacement

Originally built: 1955

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  August 24, 2010

Construction completed:  October 13, 2010 (Closed 47 days)

PROJECT COMPLETE

Crooked CreekRoute E Crooked Creek

Before                    After

 

Route: Route E

Bridge location:  Crooked Creek

Work to be done:  Bridge replacement

Originally built: 1932

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  September 13, 2010

Construction completed:  October 5, 2010 (Closed 35 days)

 

Harrison County                                Harrison County Bridge Map - Click here

PROJECT COMPLETE

U.S. 69 at Big CreekU.S. 69 Hwy. Big Creek

Before                 After

 

Route: U.S. 69 Hwy

Bridge location: Big Creek

Work to be done:  Bridge replacement

Originally built: 1928

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  September 13, 2010

Construction completed:  November 10, 2010 (Closed 57 days)

 

     

PROJECT COMPLETE

U.S. 69 Hwy. at Big Creek OverflowU.S. 69 Hwy. Big Creek Overflow

Before                 After

 

Route: U.S. 69 Hwy.

Bridge location: Big Creek Overflow

Work to be done: Bridge replacement  

Originally built: 1928

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date: October 4, 2010                                                            Construction completed:  November 10, 2010 (Closed 36 days)

     

PROJECT COMPLETE

U.S. 136 Hwy. at Sugar CreekSugar Creek

Before                 After

 

Route: U.S. 136 Hwy.

Bridge location: Sugar Creek

Work to be done: Bridge replacement  

Originally built: 1937

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  July 18, 2011

Construction completed:  August 17, 2011 (Closed 29 days)  

Detour map:  Click here for U.S. 136 Hwy. Detour

     

PROJECT COMPLETE

Route MM at Fox CreekRoute MM Fox Creek

Before                 After

 

Route: Route MM

Bridge location: Fox Creek

Work to be done: Bridge redeck

Originally built: 1962

Award amount:  $135,150.00

Awarded to:  Chester Bross Construction Co.

Closure date:  August 10, 2010

Construction completed:  September 21, 2010 (Closed 42 days)

Detour map: Click here for Route MM Detour

     

PROJECT COMPLETE

Big Muddy CreekBig Muddy Creek

Before                     After

 

Route: Route M

Bridge location: Big Muddy Creek  

Work to be done: Bridge redeck

Originally built: 1957                                  

Award amount:  $234,973.32

Awarded to:  Loch Sand and Construction Co. 

Closure Date:  May 6, 2009

Construction completed:  June 9, 2009 (Closed 34 days)

Bridge Painting Project: Scheduled For 2010

 

     

PROJECT COMPLETE

Route UU at Indian CreekRoute UU Indian Creek

Before                 After

 

Route: Route UU

Bridge location: Indian Creek

Work to be done:  Bridge replacement  

Originally built: 1958

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  November 1, 2010

Construction completed:  December 23, 2010  (Closed 52 days)

 

     

PROJECT COMPLETE

Route KK at Shain CreekRoute KK Shain Creek

Before                 After

 

Route: Route KK

Bridge location: Shain Creek

Work to be done: Bridge replacement  

Originally built:  1959

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  April 26, 2010

Construction completed: June 9, 2010 (Closed 44 days)  

     

PROJECT COMPLETE

Route HH at Lotts CreekLotts Creek

Before                     After

 

Route: Route HH

Bridge location: Lotts Creek

Work to be done: Bridge redeck 
Originally built:
1960
Award amount: $268,942.92
Awarded to:  Loch Sand and Construction Co.
Closure date: May 26, 2009                                                                        

Construction completed:  July 8, 2009 (Closed 43 days)                                Bridge Painting Project: Scheduled For 2010

     

PROJECT COMPLETE
Route MM at Sugar CreekRoute MM Sugar Creek

Before                 After

 

Route: Route MM

Bridge location: Sugar Creek

Work to be done:  Bridge redeck  

Originally built: 1962 

Award amount:  $174,338.00

Awarded to:  Chester Bross Construction Co.

Closure date:  September 20, 2010

Construction completed:  October 29, 2010 (Closed 39 days)

                                                                                                                               

     

PROJECT COMPLETE

Route N at Brush CreekRoute N

Before                  After 

 

Route: Route N

Bridge location:  Brush Creek  

Work to be done: Bridge replacement  

Originally built: 1950

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  April 12, 2010

Construction Completed:  June 1, 2010 (Closed 51 days)

     

PROJECT COMPLETE

Route O at Indian CreekRoute O Indian Creek

Before                 After 

 

Route: Route O

Bridge location: Indian Creek

Work to be done: Bridge replacement

Originally built: 1950

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date : August 16, 2010

Construction completed:  September 24, 2010 (Closed 39 days)

     

PROJECT COMPLETE

Route O at Donaby CreekDonaby

Before                 After 

 

Route:  Route O

Bridge location: Donaby Creek

Work to be done: Bridge replacement

Originally built: 1950

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  July 6, 2010

Construction Completed:  August 13, 2010 (Closed 38 days)

     

PROJECT COMPLETE

Route F at Panther CreekRoute F Panther Creek

Before                 After

 

Route: Route F

Bridge location: Panther Creek

Work to be done:  Bridge replacement

Originally built: 1951

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  September 22, 2010

Construction completed:  October 28, 2010 (Closed 36 days)

     

PROJECT COMPLETE

Route CC at Cat CreekCat Creek

Before                   After

 

Route: Route CC

Bridge location: Cat Creek

Work to be done:  Bridge replacement  

Originally built: 1953

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  October 10, 2011 

Construction completed:  November 4, 2011 (Closed 24 days)

Detour map:  Click here for Route CC Detour

     

PROJECT COMPLETE

Route Z at Shain CreekRoute Z Harrison County

Before                  After 

 

Route: Route Z

Bridge location: Shain Creek

Work to be done: Bridge replacement

Originally built: 1954

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  July 14, 2010

Construction completed:  September 3, 2010 (Closed 51 days)  

     

PROJECT COMPLETE

Route M at West Fork Big CreekRoute M West Fork Big Creek

Before                 After 

 

Route: Route M

Bridge location: West Fork Big Creek  

Work to be done: Bridge replacement  

Originally built: 1955

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  August 18, 2010

Construction completed:  October 5, 2010 (Closed 49 days)

     

PROJECT COMPLETE

Route Y at Trail CreekRoute Y Trail Creek

Before                 After 

 

Route: Route Y

Bridge location: Trail Creek  

Work to be done: Bridge replacement 

Originally built: 1956

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  October 7, 2010

Construction completed:  November 24, 2010 (Closed 47 days)  

     

PROJECT COMPLETE

Route AA at Big CreekRoute AA Big Creek

Before                 After

 

Route: Route AA

Bridge location: Big Creek

Work to be done: Bridge redeck

Originally built: 1962

Award amount:  $353,788.00

Awarded to:  Chester Bross Construction Co.

Closure date:  August 30, 2010

Construction completed:  October 29, 2010 (Closed 60 days)

     

PROJECT COMPLETE

Route B BridgeRoute B Bridge

Before                After  

 

Route: Route B

Bridge location: BR

Work to be done:  Bridge replacement

Originally built: 1931

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  June 7, 2010

Construction completed: July 12, 2010 (Closed 36 days)  

   

PROJECT COMPLETE

Route B at Panther CreekPanther Creek

Before                 After 

 

Route: Route B

Bridge location: Panther Creek

Work to be done: Bridge replacement

Originally built: 1931

Awarded to:  KTU Constructors (Design-Build Contract)

Closure Date :  July 19, 2010

Construction completed:  August 25, 2010 (Closed 38 days)

     

PROJECT COMPLETE

Route B at Drainage DitchRoute B

Before                  After

 

Route: Route B

Bridge location: Drainage Ditch

Work to be done:  Bridge replacement

Originally built: 1931

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  May 25, 2010

Construction completed:  June 23, 2010 (Closed 30 days)

     

PROJECT COMPLETE

MO 46at West Fork Big CreekWest Fork Big Creek

Before                 After

 

Route: MO 46

Bridge location: West Fork Big Creek  

Work to be done:  Bridge replacement

Originally built: 1946

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  June 25, 2012

Construction completed:  August 8, 2012 (Closed 44 days)

Detour map:  Click here for MO 46 Detour

     

PROJECT COMPLETE

MO 46 at East Fork Big CreekMO 46 Bridge

Before                 After  

 

Route: MO 46

Bridge location: East Fork Big Creek  

Work to be done: Bridge replacement

Originally built: 1946

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date: June 1, 2010

Construction completed:  July 23, 2010 (Closed 53 days)

     

PROJECT COMPLETE

MO 46 Shain CreekMO 46 Shain Creek

Before                 After 

 

Route: MO 46

Bridge location: Shain Creek  

Work to be done: Bridge replacement

Originally built: 1946

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  March 22, 2010

Construction completed:  May 14, 2010 (Closed 54 days) 

     

PROJECT COMPLETE

Route A at Big Panther CreekRoute A

Before                 After 

 

Route: Route A

Bridge location: Big Panther Creek

Work to be done:  Bridge replacement

Originally built: 1949

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  April 5, 2010

Construction completed:  May 18, 2010 (Closed 44 days)

 

Holt County                                       Holt County Bridge Map - Click here

PROJECT COMPLETE

U.S. 59 Hwy at Little Tarkio CreekLittle Tarkio Creek

Before                 After

 

Route: U.S. 59 Hwy.

Bridge location: Little Tarkio Creek

Work to be done:  Bridge replacement

Originally built: 1926

Awarded to:  KTU Constructors (Design-Build Contract)    

Closed for construction:  August 22 , 2011

Construction completed:  October 11, 2011  (Closed 49 days)  

Detour map: Click here for US 59 Hwy. Detour

 
     

PROJECT COMPLETE

Route B at Nichols CreekHolt County Route B

Before                   After

PROJECT COMPLETE

Route B at Nichols CreekHolt B Nichols Creek North

Before                 After

 

Route: Route B

Bridge location: Nichols Creek (South)

Work to be done: Bridge replacement

Originally built: 1953

Awarded to:  KTU Constructors (Design-Build Contract)    

Closure date:  April 4, 2011 

Construction completed:  May 9, 2011 (Closed 35 days)

Detour map: Click here for Route B Detour

 

 

Route: Route B

Bridge location: Nichols Creek (North)

Work to be done: Bridge replacement

Originally built: 1931

Awarded to:  KTU Constructors (Design-Build Contract)    

Closed for construction:  May 9, 2011 

Construction completed: June 29, 2011 (Closed 51 days)

Detour map:  Click here for Route B Detour

 

PROJECT COMPLETE

Route B at Lincoln CreekLincoln Creek

Before                 After

 

Route: Route B

Bridge location: Lincoln Creek

Work to be done: Bridge replacement

Originally built: 1954

Awarded to:  KTU Constructors (Design-Build Contract)    

Closed for construction:  June 27, 2011

Construction completed: August 24, 2011 (Closed 55 days)

Detour map:  Click here for Route B Detour

PROJECT COMPLETE

MO 111 at Old Channel of Big Tarkio MO 111

Before                 After

 

Route: MO 111

Bridge location: Old Channel of Big Tarkio

Work to be done: Bridge replacement

Originally built: 1956

Awarded to:  KTU Constructors (Design-Build Contract)    

Closed for construction: April 16, 2012

Construction completed: May 22, 2012 (Closed 37 days)

Detour map: Click here for MO 111 Detour

     

PROJECT COMPLETE

MO 111 at Cannon CreekCannon Creek

Before                 After

 

Route: MO 111

Bridge location: Cannon Creek

Work to be done: Bridge replacement

Originally built: 1956

Awarded to:  KTU Constructors (Design-Build Contract)    

Closed for construction:  March 5, 2012 

Construction completed: April 4, 2012 (Closed 30 days)

Detour map:  Click here for MO 111 Detour

     

PROJECT COMPLETE

Route C at Mid Branch of Squaw CreekRoute C

Before                 After

 

Route: Route C

Bridge location: Mid Branch of Squaw Creek

Work to be done: Bridge replacement

Originally built: 1955

Awarded to:  KTU Constructors (Design-Build Contract)    

Closed for construction:  March 19, 2012 

Construction completed: May 1, 2012 (Closed 43 days)

Detour map: Click here for Route C Detour

     

PROJECT COMPLETE

Route C at Squaw CreekSquaw Creek

Before                 After

 

Route: Route C

Bridge location: Squaw Creek

Work to be done: Bridge replacement

Originally built: 1955

Awarded to:  KTU Constructors (Design-Build Contract)    

Closure date:  October 3, 2011 

Construction completed: November 1, 2011 (Closed 28 days)

Detour map:  Click here for Route C Detour

     

PROJECT COMPLETE

Route N at East Branch of Squaw CreekRoute N  East Branch

Before                 After

 

Route: Route N

Bridge location: East Branch of Squaw Creek

Work to be done: Bridge replacement

Originally built: 1947

Awarded to:  KTU Constructors (Design-Build Contract)    

Closure date: March 21, 2011  

Construction completed: May 27, 2011 (Closed 67 days)  

Detour map: Click here for Route N Detour

     

PROJECT COMPLETE

Route N at Mid Branch of Squaw CreekRoute N Mid Branch Squaw Creek

Before                 After

 

Route: Route N

Bridge location: Mid Branch of Squaw Creek

Work to be done: Bridge replacement

Originally built: 1947

Awarded to:  KTU Constructors (Design-Build Contract)    

Closure date:  May 26, 2011 

Construction completed:  July 18, 2011 (Closed 53 days)

Detour map:  Click here for Route N Detour

     

PROJECT COMPLETE

MO 111 at Corn CreekMO 111 Corn Creek

Before                 After

 

Route: MO 111

Bridge location: Corn Creek

Work to be done: Bridge replacement

Originally built: 1936

Awarded to:  KTU Constructors (Design-Build Contract)    

Closure date:  April 11, 2011 

Construction completed:  May 26, 2011 (Closed 45 days)

Detour map: Click here for MO 111 Detour

     

PROJECT COMPLETE

Route C at Wildcat CreekWildcat Creek

Before                  After

 

Route: Route C

Bridge location: Wildcat Creek

Work to be done: Bridge replacement

Originally built: 1949

Awarded to:  KTU Constructors (Design-Build Contract)    

Closed for construction:  September 6, 2011

Construction completed:  October 5, 2011 (Closed 29 days)  

Detour map:  Click here for Route C Detour 

     

PROJECT COMPLETE

Route C at Minnesota Valley CreekMinnesota Valley Creek

Before                  After

 

Route: Route C

Bridge location: Minnesota Valley Creek

Work to be done: Bridge replacement

Originally built: 1947

Awarded to:  KTU Constructors (Design-Build Contract)    

Closure date:  July 18, 2011

Construction completed:  September 2, 2011 (Closed 45 days)

Detour map:  Click here for Route C Detour

 

 Linn County                                  Linn County Bridge Map - Click here

PROJECT COMPLETE

Parsons CreekRoute DD Parsons Creek

Before                     After

 

Route: DD

Bridge location: Parsons Creek

Work to be done:  Bridge replacement

Originally built: 1951

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  September 27, 2010

Construction completed:  October 29, 2010 (Closed 35 days)

 

PROJECT COMPLETE

Big Muddy CreekRoute E Big Muddy Creek

Before                     After

 

Route: E

Bridge location: Big Muddy Creek

Work to be done:  Bridge replacement

Originally built: 1952

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  October 7, 2010

Construction completed:  Noveber 11, 2010 (Closed 44 days)

 

 Livingston County                        Livingston County Bridge Map - Click here

PROJECT COMPLETE

Old Channel Shoal CreekRoute D Old Channel Shoal Creek

Before                    After

Route: D

Bridge location: Old Channel Shoal Creek

Work to be done:  Bridge replacement

Originally built: 1954

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  July 28, 2010

Construction completed:  September 10, 2010 (Closed 43 days)

 

PROJECT COMPLETE

Old Medicine CreekOld Medicine Creek

Before                    After

 

Route: K

Bridge location: Old Medicine Creek Channel

Work to be done:  Bridge replacement

Originally built: 1938

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  July 27, 2010

Construction completed:  September 13, 2010 (Closed 33 days)

   

 

 Mercer County                                Mercer County Bride Map - Click here

PROJECT COMPLETE

Big BranchRoute P Big Branch

Before                     After

 

Route: P

Bridge location: Big Branch

Work to be done:  Bridge replacement

Originally built: 1952

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  October 18, 2010

Construction completed:  November 12, 2010 (Closed 45 days)

   

 

Nodaway County                           Nodaway County Bridge Map - Click here

PROJECT COMPLETE

US 136 Hwy. at Wildcat CreekWildcat Creek

Before                 After

 

Route: U.S. 136 Hwy.

Bridge location: Wildcat Creek

Work to be done:  Bridge replacement

Originally built: 1931

Awarded to:  KTU Constructors (Design-Build Contract)

Closed for construction:  October 3, 2011                                Construction completed:  November 17, 2011 (Closed 43 days)                                Detour map: Click here for U.S. 136 Hwy. Detour

     

PROJECT COMPLETE

US 71 Hwy. at White Cloud CreekWhite Cloud Bridge

Before                 After

 

Route: U.S. 71 Hwy.

Bridge location: White Cloud Branch

Work to be done: Bridge replacement  

Originally built: 1933

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  May 29, 2012

Construction completed:  June 29, 2012 (Closed 31 days)  

Detour map: Click here for U.S. Hwy. 71 Detour

     

PROJECT COMPLETE
Route J at Sleek CreekNodaway J Sleek Creek

Before                 After

 

Route: Route J

Bridge location: Sleek Creek  

Work to be done: Bridge replacement

Originally built: 1939

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  September 27, 2010

Construction completed:  November 2, 2010 (Closed 36 days)

 

     

PROJECT COMPLETE

MO 246 at Honey CreekMO 246 Homey Creek

Before                 After

 

Route: MO 246

Bridge location: Honey Creek

Work to be done: Bridge replacement

Originally built: 1947

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date: March 28, 2011

Construction completed:  June 17, 2011 (Closed 81 days)

Detour map: Click here for MO 246 Detour

     

PROJECT COMPLETE

MO 246 at Brushy CreekBrushy Creek

Before                 After

 

Route: MO 246

Bridge location: Brushy Creek

Work to be done: Bridge replacement

Originally built: 1947

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  August 1, 2011

Construction completed:  September 2, 2011 (Closed 32 days)

Detour map: Click here for MO 246 Detour

     

PROJECT COMPLETE

Route A at Elkhorn CreekElkhorn

Before                    After

 

Route: Route A

Bridge location: Elkhorn Creek

Work to be done: Bridge redeck

Originally built: 1953

Closure date: June 5,2012

Construction completed:  July 20, 2012 (Closed 47 days)

Detour map: Click here for Route A Detour

PROJECT COMPLETE    

Route JJ at West Fork 102 RiverRoute JJ

Before                     After

 

Route: Route JJ

Bridge location: West Fork 102 River

Work to be done: Bridge redeck

Originally built: 1955

Awarded on:  March 4th

Award Amount:  $314,107.11

Awarded to:  A.M. Cohron & Sons, Inc.

Closure date:  July 27, 2009

Completion date:  September 14, 2009  (Closed 48 days)

     

PROJECT COMPLETE

Route VV at Long Branch Long Branch

Before                     After

 

Route: Route VV

Bridge location: Long Branch

Work to be done: Bridge redeck

Originally built: 1956

Closure date:  May 14, 2012

Completion date:  September 14, 2009  (Closed 44 days)

Detour map:  Click here for Route VV Detour

     

PROJECT COMPLETE

MO 246 at Norvey CreekMO 246 Norvey Creek

Before                  After

 

Route: MO 246

Bridge location: Norvey Creek

Work to be done: Bridge replacement

Originally built: 1952

Awarded to:  KTU Constructors (Design-Build Contract)

Closed date:  March 14, 2011 

Completion date: April 29, 2011 (Closed 47 days) 

     

PROJECT COMPLETE

Route NN at Honey CreekHoney Creek

Before                     After

 

Route: Route NN

Bridge location: Honey Creek

Work done: Bridge redeck

Originally built: 1955

Award amount:  $238,560.34

Awarded to:  Loch Sand and Construction Co.

Closure date: March 17, 2009

Construction completed:  April 29, 2009 (Closed 43 Days)

     

PROJECT COMPLETE

Route NN at Brushy CreekBrushy Creek

Before                     After

 

Route: Route NN

Bridge location: Brushy Creek

Work to be done: Bridge redeck

Originally built: 1955 

Award amount:  $194,738.84

Awarded to:  Loch Sand and Construction Co.

Closure date:  April 1, 2009

Construction completed:  May 12, 2009 (Closed 42 Days)

     

PROJECT COMPLETE

Route PP at Huff CreekHuff Creek

Before                     After

 

Route: Route PP

Bridge location: Huff Creek

Work to be done: Bridge redeck

Originally built: 1961

Awarded on:  September 2, 2009

Award amount:  $255,609.75

Awarded to:  Boone Construction Co.

Closure date:  October 13, 2009                                                                               Construction completed:  November 17, 2009 (Closed 35 days)

 

     

PROJECT COMPLETE

Route PP at Maupin CreekMaupin Creek after

Before                 After

 

Route: Route PP

Bridge location: Maupin Creek

Work to be done: Bridge redeck

Originally built: 1961

Awarded on:  September 2, 2009

Award amount:  $259,039.75

Awarded to:  Boone Construction Co.

Closure date: March 8, 2010                                                                       Construction completed:  April 12, 2010 (Closed 37 days)

     

PROJECT COMPLETE

Route A at Jenkins CreekRoute A Jenkins Cr

Before                   After

 

Route: Route A

Bridge location: Jenkins Creek

Work to be done: Bridge replacement

Originally built: 1930

Awarded to:  KTU Constructors (Design-Build Contract)

Closed for construction:  February 28, 2011

Construction completed:  April 22, 2011 (Closed 53 days)

Detour map:  Click here for Route A Detour

     

PROJECT COMPLETE

MO 113 at Nodaway RiverNodaway River

Before                 After

 

Route: MO 113

Bridge location: Nodaway River

Work to be done: Bridge replacement

Originally built: 1932

Awarded to:  KTU Constructors (Design-Build Contract)

Closed for construction:  July 5, 2011

Construction completed:  September 22, 2011 (Closed 77 days)  

Detour map:  Click here for MO 113 Detour

     

PROJECT COMPLETE

Nodaway River OverflowNodaway River South Overflow

Before                 After

 

Route: MO 113

Bridge location: Nodaway River South Overflow

Work to be done: Bridge replacement

Originally built: 1932

Awarded to:  KTU Constructors (Design-Build Contract)

Closed for construction:  May 10, 2011

Construction completed:  July 5, 2011  (Closed 56 days)

Detour map: Click here for MO 113 Detour

     

PROJECT COMPLETE

MO 113 at Nodaway River OverflowNodaway River North Overflow

Before                  After

 

Route: MO 113

Bridge location: Nodaway River North Overflow

Work to be done: Bridge replacement

Originally built: 1932

Awarded to:  KTU Constructors (Design-Build Contract)

Closed for construction:  March 21, 2011

Construction completed:  May 10, 2011 (Closed 49 days)

Detour map:  Click here for MO 113 Detour

     

PROJECT COMPLETE

MO 113 at Cayhoga CreekMO 113 Cayhoga Creek

Before                 After

 

Route: MO 113

Bridge location: Cayhoga Creek

Work to be done: Bridge replacement

Originally built: 1950

Awarded to:  KTU Constructors (Design-Build Contract)

Closed for construction:  June 2, 2011

Construction completed:  July 1, 2011 (Closed 28 days)

Detour map:  Click here for MO 113 Detour

     

PROJECT COMPLETE

MO 113 at Bowman CreekBowman Branch

Before                 After

 

Route: MO 113

Bridge location: Bowman Branch

Work to be done: Bridge replacement

Originally built: 1934

Awarded to:  KTU Constructors (Design-Build Contract)

Closed for construction:  July 6, 2011

Construction completed:  August 8, 2011 (Closed 32 days)

Detour map:  Click here for MO 113 Detour

     

PROJECT COMPLETE

MO 113 At Sand CreekSand Creek

Before                    After

 

Route: MO 113

Bridge location: Sand Creek

Work to be done: Bridge replacement

Originally built: 1934

Awarded to:  KTU Constructors (Design-Build Contract)

Closed for construction:  April 2, 2012

Construction completed: May 7, 2012 (Closed 36 days)

Detour map:  Click here for MO 113 Detour

     

PROJECT COMPLETE

Route F at Mozingo CreekRoute F Mozingo Creek

Before                 After

 

Route: Route F

Bridge location: Mozingo Creek

Work to be done: Bridge replacement

Originally built: 1936

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  August 30, 2010

Construction completed:  October 5, 2010 (Closed 35 days)

 

Putnam County -                           Putnam County Bridge Map - Click here

PROJECT COMPLETE

Shankton BranchRoute M Shankton Bridge

Before                      After

 

Route: Route M

Bridge location: Shankton Branch

Work to be done: Bridge replacement

Originally built: 1954

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  September 20, 2010

Construction completed:  October 23, 2010 (Closed 42 days)

PROJECT COMPLETE

Barber CreekRoute 139 Barber Creek

Before                    After

 

Route: Route 139

Bridge location: Barber Creek

Work to be done: Bridge replacement

Originally built: 1933

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  July 19, 2010

Construction completed:  October 2, 2010 (Closed 45 days)

PROJECT COMPLETE

West Locust CreekRoute EE West Locust Creek

Before                     After

 

Route: Route EE

Bridge location: West Locust Creek

Work to be done: Bridge deck replacement

Originally built: 1960

Closure date:  March 8, 2010

Construction completed:  April 21, 2010 (Closed 44 days)

PROJECT COMPLETE

East Locust CreekRoute 136 East Locust Creek

Before                    After

 

Route: Route 136

Bridge location: East Locust Creek

Work to be done: Bridge replacement

Originally built: 1931

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  August 2, 2010

Construction completed:  September 23, 2010 (Closed 56 days)

PROJECT COMPLETE

Blackbird CreekRoute 5 Blackbird Creek

Before                     After

 

Route: Route 5

Bridge location: Blackbird Creek

Work to be done: Bridge replacement

Originally built: 1932

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  June 9 , 2010

Construction completed:  July 23, 2010 (Closed 42 days)

Sullivan County                             Sullivan County Bridge Map - Click here

PROJECT COMPLETE
StreamRoute 139 Stream

Before                     After

 

Route: Route 139

Bridge location: Unnamed Stream

Work to be done: Bridge replacement

Originally built: 1933

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  November 3, 2010

Construction completed:  November 30, 2010 (Closed 35 days)

PROJECT COMPLETE

Muddy CreekRoute 6 Muddy Creek

Before                    After

 

Route: Route 6

Bridge location: Muddy Creek

Work to be done: Bridge replacement

Originally built: 1932

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  October 18, 2010

Construction completed:  November 23, 2010 (Closed 31 days)

PROJECT COMPLETE
Elmwood CreekElmwood Creek

Before                    After

 

Route: Route 5

Bridge location: Elmwood Creek

Work to be done: Bridge replacement

Originally built: 1929

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  September 29, 2010

Construction completed:  October 27, 2010 (Closed 31 days)

PROJECT COMPLETE
Little Yellow CreekRoute 129 Little Yellow Creek

Before                     After

 

Route: Route 129

Bridge location: Little Yellow Creek

Work to be done: Bridge replacement

Originally built: 1931

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  September 29, 2010

Construction completed:  November 2, 2010 (Closed 36 days)

PROJECT COMPLETE

Little Yellow CreekLittle Yellow Creek

Before                   After

 

Route:  Route C

Bridge location: Little Yellow Creek

Work to be done: Bridge replacement

Originally built: 1952

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  June 6, 2011

Construction completed:  July 12, 2011 (Closed 35 days)  

 

PROJECT COMPLETE
Long BranchRoute O Long Branch

Before                    After

 

Route:  Route O

Bridge location: Long Branch

Work to be done: Bridge replacement

Originally built: 1954

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  October 11, 2010 

Construction completed:  December 4, 2010 (Closed 42 days)

PROJECT COMPLETE

Mussel CreekMussel Creek

Before                 After

 

Route:  Route H

Bridge location: Mussel Creek

Work to be done: Bridge replacement

Originally built: 1955

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  July 11, 2011

Construction completed:  August 29, 2011 (Closed 48 days)

PROJECT COMPLETE
Yellow CreekRoute N Yellow Creek

Before                    After

 

Route:  Route N

Bridge location: Yellow Creek

Work to be done: Bridge replacement

Originally built: 1923

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date: May 24, 2010

Construction completed:  July 10, 2010 (Closed 47 days)

Worth County                                Worth County Bridge Map - Click here

PROJECT COMPLETE

Route PP at Mid Fork Grand RiverMiddle Fork Grand River

Before                 After

 

Route: Route PP

Bridge location: Middle Fork Grand River

Work to be done: Bridge replacement  

Originally built: 1958

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  August 1, 2011

Construction completed:  September 23, 2011 (Closed 52 days)

Detour map:  Click here for Route PP Detour

     

PROJECT COMPLETE

Route C at Little Rock CreekLittle Rock Creek

Before                 After

 

Route: Route C

Bridge location: Little Rock Creek

Work to be done: Bridge replacement  

Originally built: 1951

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  September 19, 2011

Construction completed:  November 1, 2011  (Closed 42 days)

Detour map:  Click here for Route C Detour

     

PROJECT COMPLETE

Route W at Bear CreekRoute K Clinton County

Before                  After

 

Route: Route W

Bridge location: Bear Creek

Work to be done: Bridge replacement  

Originally built: 1937

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  March 21, 2011

Construction completed:  April 27, 2011 (Closed 37 days)

Detour map: Click here for Route W Detour

     

PROJECT COMPLETE

Route T at Lotts Creek

Before 

 

Route: Route T

Bridge location: Lotts Creek

Work to be done: Bridge replacement  

Originally built: 1934

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  July 9, 2012

Construction completed:  August 20, 2012 (Closed 37 days)

Detour map:  Click here for Route T Detour

     

PROJECT COMPLETE

Route W at Oxcart CreekRoute W Oxcart Creek

Before                 After

 

Route: Route W

Bridge location: Oxcart Creek

Work to be done: Bridge replacement  

Originally built: 1948

Awarded to:  KTU Constructors (Design-Build Contract)

Closure date:  April 27, 2011

Construction completed:  June 6, 2011

Detour map:  Click here for Route W Detour

 

 
 
 
`
 
District Map
Northwest District
spacer
Traveler Information
Traveler Map
map
call, cell, mobile, phone iconText Alerts - Sign Up!
spacer
Quick Links
Your Local Area Engineer
Report a Road Concern
Solar Eclipse
Highway Plans and Microfilm Request
Request a Map
spacer
Your Local MoDOT
Get your local district information.
Districts Map
Northwest Northeast Kansas City Central St. Louis Southwest Southeast
About Us
How Do I...
Contact Us
Missouri Department of Transportation
Central Office
105 W. Capitol Avenue
Jefferson City, MO 65102
1-888-ASK-MODOT (275-6636)
1-866-831-6277 (Motor Carrier Services)
Drivers License Offices
horz_bar
| | |
Missouri State Government
 
© 2013 Missouri Department of Transportation. All Rights Reserved.   Privacy Policy.
 
 
Atchison Holt Nodaway Andrew Buchanan Worth Gentry DeKalb Clinton Harrison Daviess Caldwell Mercer Grundy Livingston Carroll Putnam Sullivan Linn Chariton Northwest Northeast Kansas City Central St. Louis Southwest Southeast IPhone Android Facebook Twitter Flickr Pinterest Blog YouTube RSS