Construction Projects
Route 63 Adair & Macon Counties - Resurface 23 Miles.
Location(s): From Route 6 in Adair County to Route M at Atlanta in Macon County.
Traffic Impact: N/A
Project Status: Completed
Estimated Completion: Completed as Promised (Fall 2008)
More information about this project.
Maintenance Projects
Back to Top

Construction Projects
Route 240 - Partial Replacement of the Missouri River Bridge at Glasgow.
Location(s): Saline/Howard Counties - Missouri River Bridge at Glasgow.
Traffic Impact: Ferry service is active.
Project Status: Complete
Estimated Completion: Completed as Promised (Fall 2009)
More information about this project.
Route 41 - Partial Replacement of the Missouri River Bridge at Miami.
Location(s): Missouri River Bridge at Miami on Rte. 41 Carroll/Saline Counties.
Traffic Impact: Bridge will be closed to traffic for up to 12 months during the rehabilitation. Research to provide alternate transportation during the closure is ongoing.
Project Status: Active
Estimated Completion: Oct. 2010
More information about this project.
Maintenance Projects
Route 65 - Overlay - Aug. 28 to Nov. 25 - 6 a.m. to 7 p.m. - Traffic reduced to one lane from Chillicothe south to the city limits of Carrollton
Route E - Culvert Replacement - Nov. 2 to Nov. 13 - 7:30 a.m. to 3 p.m. - Section of roadway closed from Rte. EE near Carrollton to Rte. D.
Back to Top
Construction Projects
Maintenance Projects
Route 139 - Weight Restriction of 15 ton on bridge over Stanley Creek west of Rte. EE near Sumner - Oct. 10 to Nov. 30 - Vehicles weighing over 15 tons must find alternate routes.
Route 139 - Bridge Repairs - Oct. 8 to Nov. 30 - 8:30 am to 4:30 p.m. - Traffic reduced to one lane one-half mile west of Rte. RA. Vehicles wider than 12 feet must seek an alternate route.
Route JJ - BNSF crossing repairs - Nov. 4 at 8 a.m. to Nov. 6 at 5 p.m. - Section of roadway closed approximately one mile north of the Route E intersection.
Route 24 - Bridge Repairs - Nov. 3 to Nov. 5 - 7:30 a.m. to 5:00 p.m. - Traffic reduced to one lane one mile west of Route KK.
Route 129 North - Culvert Replacment - Nov. 5 - 8 a.m. to 2:30 p.m. - Section of roadway closed from jct. of Rte. W north of Salisbury and will continue south to end at the jct. of Rte. HH.
Back to Top
Construction Projects
Maintenance Projects
Back to Top
Construction Projects
Route 240 Howard & Saline Counties - Partial Replacement of the Missouri River Bridge at Glasgow.
Location(s): Missouri River Bridge at Glasgow.
Traffic Impact: Ferry service is active.
Project Status: Complete
Estimated Completion: Completed as Promised (Fall 2009)
More information about this project.
Maintenance Projects
Route 240 - Resurfacing - Oct. 19 to Nov. 9 - 7 a.m. to 7 p.m. - Road reduced to one lane from Route 124 to Route 40.
Back to Top

Construction Projects
Maintenance Projects
Back to Top

Construction Projects
Maintenance Projects
Route 65 - Overlay - Aug. 28 to Nov. 25 - 6 a.m. to 7 p.m. - Traffic reduced to one lane from Chillicothe south to the city limits of Carrollton.
Back to Top

Construction Projects
Route 36 - Construct 22 miles of additional lanes from Shelbina to Macon.
This section is part of the entire project to four lane Route 36 between Hannibal and Macon.
Location(s): Contractors currently working in various locations between Macon and Shelbina.
Traffic Impact: None at this time
Project Status: Active
Estimated Completion: 2010
More information about this project.
Maintenance Projects
Back to Top

Construction Projects
Maintenance Projects
Back to Top

Construction Projects
Maintenance Projects
Back to Top

Construction Projects
Route 24 - Bridge Replacements.
Location(s): Over East Fork of the Chariton River just east of Clifton Hill.
Traffic Impact: N/A
Project Status: Completed
Estimated Completion: Completed as Promised (Fall 2008)
Maintenance Projects
Back to Top

Construction Projects
Route 240 - Partial Replacement of the Missouri River Bridge at Glasgow.
Location(s): Saline/Howard Counties - Missouri River Bridge at Glasgow.
Traffic Impact: Ferry service is active.
Project Status: Complete
Estimated Completion: Completed as Promised (Fall 2009)
More information about this project.
Route 41 - Partial Replacement of the Missouri River Bridge at Miami.
Location(s): Missouri River Bridge at Miami on Rte. 41 Carroll/Saline Counties.
Traffic Impact: Bridge will be closed to traffic for up to 12 months during the rehabilitation. Research to provide alternate transportation during the closure is ongoing.
Project Status: Active
Estimated Completion: Oct. 2010
More information about this project.
Maintenance Projects
Route AA- Culvert Replacement- Nov. 5 - 7 a.m. to 3 p.m. - Roadway closed one and one-half miles north of route H continuing north for approximately one-half mile.