Hollister/U.S. 65 Interchange
Construction
Update for Week of April 25
Work scheduled: Rock hauling and dirt grading planned east side
of U.S. 65 south of Mall Road.
Box culvert installation across Industrial Boulevard.
Construction of new Business 65 overpass.
Retaining wall construction at southwest corner of U.S. 65 and
Route V.
Installing storm drain system along Route V near College of the
Ozarks.
No night work or blasting planned.
Impact on Traffic: Traffic may be stopped for short periods on
Mall Road and Birch Road to allow dump trucks hauling rock to
cross the road.
One-lane traffic possible on Industrial Boulevard.
All other work planned should take place AWAY from traffic.
Work zone speed limit on U.S. 65:
45 mph.
Project background:
Construction of U.S. 65/Business 65 interchange and overpass for
Business 65 north of new interchange and widening of U.S. 65 to
four lanes along 1.6 miles (2,000 feet north of Bus. 65/Route
V to just south of Route 165.)
Cost: $19.2 million (low bid), shared by MoDOT, City of Hollister
and Taney County.
Prime contractor: W.A. Ellis Construction of Independence.
Scheduled completion: Fall 2006.