June 10, 2005

Traffic Backups Expected for Two Months
During Pavement Work on I-44 at Springfield


MoDOT, District 8, Springfield -- Lane closings and lane shifts through late September are expected to generate traffic backups on Interstate 44 just east of Springfield when a much-needed pavement reconstruction project begins Monday, June 20.

A one-mile section of westbound I-44 will be rebuilt and a one-mile section of eastbound I-44 resurfaced at the Route 744 interchange east of Springfield, the Missouri Department of Transportation said.

The reconstruction of the westbound lanes will be done by closing one lane at a time round the clock for several weeks.

One westbound lane will remain open at all times.

When the eastbound lanes are resurfaced, drivers can expect one eastbound lane to be closed during daytime hours. However, both lanes will be opened to traffic at night.

The westbound I-44 speed limit will be reduced to 60 mph round the clock starting July 5.

The eastbound I-44 speed limit will be reduced to 60 mph when a lane is closed and crews are working.

Rain or other delays will cause changes in the work schedule.

The contractor doing the work is Idecker, Inc. of St. Joseph, for a low-bid amount of $2.4 million.

Here's a look at the project's schedule:

* Week of June 13 -- Contractor crews move in and begin setting work zone signs and preparing for the project to begin on June 20. No lane closings are expected.

* June 20-July 5 -- The westbound I-44 passing lane will be closed to allow crews to remove the shoulder of the interstate and rebuild it to handle traffic that will be shifted on to it during the reconstruction of the westbound driving lane. The westbound passing lane will be closed during this work.

During the Fourth of July holiday weekend, there will be no lane closings in either direction on I-44.

* July 5 -- The westbound I-44 driving lane is scheduled to be closed round the clock until mid-August. The old concrete pavement will be removed. Crews will haul in new base rock and will pour concrete to rebuild the driving lane. Westbound traffic will be shifted into one lane and will travel on a portion of the shoulder.

* August 16 -- The westbound I-44 passing lane is scheduled to be closed round the clock until late September to allow crews to tear out the old pavement, haul in new base rock and pour new concrete pavement.

* July 7 - August 10 -- One eastbound lane is scheduled to be closed during the day to allow contractor crews to repair the pavement, grind off the old pavement and lay asphalt to resurface the road. One eastbound lane will be closed. The lane closings will take place during daytime hours with both eastbound lanes opened at night.

(For more information, call MoDOT in Springfield at 417-895-7600.)

 

 

   
   