Hollister/U.S. 65 Interchange
Construction
Update for Week of August 22
Traffic Alert!
* U.S. 65 closed at night for 15 to 45 minutes between 10 p.m.
and 6 a.m. Monday through Thursday nights. Bridge girders being
installed for new Business 65 overpass.
Work scheduled:
* Rock blasted two to three times each day along U.S. 65 near
Gage Drive in area of interchange construction
* Concrete poured for curb and gutter and traffic signal bases
near Industrial Boulevard and Birch Road
* Drain pipe installation and dirt grading and hauling along Route
V near College of the Ozarks
* Construction of new Business 65 overpass bridge
Impact on Traffic:
* U.S. 65 traffic stopped about 5 minutes at a time for blasting
near roadway
* Two-way traffic on U.S. 65 shifted to temporary bypass (new
northbound lanes) east of existing lanes
* Heavy equipment near roadway and trucks entering/leaving construction
areas on Route V and Gage Drive west of U.S. 65
* Occasional one-lane traffic on Industrial Boulevard and Birch
Road
Most work taking place AWAY from traffic
Note: Large trucks
and other vehicles towing trailers should use Birch Road to access
shopping center because turning radius at Mall Road is tighter
Work zone speed limit on U.S. 65 Temporary Bypass: 35 mph.
Project background:
* Construction of U.S. 65/Business 65 interchange and separate
overpass bridge for Business 65 north of new interchange
* Widening of U.S. 65 to four lanes along 1.6 miles (2,000 feet
north of Bus. 65/Route V to just south of Route 165)
* Cost: $19.2 million (low bid), shared by MoDOT, City of Hollister
and Taney County
* Prime contractor: W.A. Ellis Construction of Independence
* Scheduled completion: Fall 2006
(For more information, call MoDOT in Springfield at 417-895-7600