Interstate 470 Corridor



Project Details:

I-470 and Rt. 50

 

comment

verticle rule
Project status: This project is complete.

 

Why is MoDOT doing this project?

Growth in Lee’s Summit prompted a new Strother Road Interchange to improve access between Woods Chapel Road and Colbern Road and allow greater opportunities for commercial and business development along the corridor.    

What is the project time line?

Crews completed the new bridges on north and southbound lanes of I-470. The entire project was complete by September 1, 2010.

How is this project funded?  

In addition to $3 million previously earmarked, the City of Lee's Summit offered an additional $5 million for the auxiliary lanes. A Transportation Development District (TDD) , including developers within the vicinity of the project, a Tax Increment Financing (TIF) plan, and Lee's Summit funding sources, to contribute to roadway infrastructure improvements, including the interchange.

How do I learn more?

For more information, review the project maps and materials listed in the left column. You can also submit a comment, send an e-mail or give us a call. Lend your voice to the transportation process!