Project Description
Construction work on the Lafayette Street interchange project has begun in Jefferson City. This project is a large two-year project encompassing multiple improvements along U.S. Route 50 near Lafayette Street, including:

• A new interchange at U.S. Route 50 and Lafayette Street
• The addition of a lane in each direction on Route 50 (Whitton Expressway) from Monroe Street to Lafayette Street and from Lafayette to Clark Avenue.
• The replacement of three bridges along the corridor: the Chestnut Street bridge over Route 50, the Jackson Street bridge over Route 50 and the Route 50 bridge over Lafayette Street.
• Two new bridges will be built as part of the ramps on the new Route 50 interchange.
• Reconstruction of pavement on Lafayette Street from Elm Street to East Handley Way.
• The Clark Avenue bridge over Route 50 will be rehabilitated. Pavement north and south of the bridge to the ramp intersections will also be reconstructed.

Project Information
Contractor: Emery Sapp and Sons, Inc.
Contract Cost: Estimated $20 million
MoDOT Project Administration: Jefferson City Project Office 
Estimated Completion Date: Fall of 2016

Contract Progress % Complete: 65%

Weekly Project Updates

All work listed below is subject to change
depending on weather conditions

Scheduled Work During the Week of May 23 (please note that all activities and schedules are weather permitting): Contractors will be drilling footings for sound walls west of Chestnut Street, grading the eastbound U.S. Route 50/63 lanes from the bridge to Monroe Street, working on Lafayette Street to East Miller and washing/staining MSE walls at Lafayette Street. Work will also continue on the MSE walls south of 50/63 at Jackson Street. Eastbound/Southbound lane closures are likely during the week of May 23 for paving operations.

 

NOTE:  There will be periodic lane closures in the driving lane of eastbound Route 50/63 from 9 a.m. to 3 p.m. Sunday, May 22 thru Saturday, May 28 from Monroe Street to Chestnut Street.

Current Traffic Impacts:

  • Both eastbound lanes of Route 50/63 are being diverted onto the newly constructed westbound lanes and across the recently built westbound Route 50/63 bridge over Lafayette Street.
  • The eastbound on ramp from Lafayette Street to Route 50/63 is closed.
  • Both westbound lanes of Route 50/63 near Lafayette Street are being diverted down the new Lafayette off ramp. Traffic continues across Lafayette Street, travel up the new Lafayette on ramp and back onto westbound 50/63.
  • Motorists do not have access to Lafayette Street from either bypass.
  • The Clark Avenue on ramp from westbound 50/63 remains closed.
  • All of the above traffic impacts are anticipated to remain in place until Summer of 2016. Two lanes will be open in each direction on 50/63 during the work, but traffic may move slower than normal during peak travel times.
  • Elm Street is permanently closed from Lafayette Street 500 feet east to Cherry Street and also from just east of Marshall Street to Lafayette Street.
  • The Jackson Street bridge is now closed for replacement and will remain closed until completion in the fall of 2016.

Two lanes will be open in each direction on Route 50/63 during the work, but traffic may move slower than normal during peak travel times. Motorists are encouraged to seek other routes, if possible.

Eastbound/Westbound Bypass Map (Effective 12-11-15)

EBWBBypass5063_12_11

Pedestrian/Cycling impacts: The east and west sidewalks along Lafayette Street from East Dunklin Street to East Miller Street, and across the Jackson Street Bridge remain closed due to construction. A temporary detour has been laid out on Monroe Street and Chestnut Street Bridge (see map below). Pedestrian and bicycle traffic is asked to use this temporary detour.

Lafayette Proj Sidewalk Map

Lafayette Sidewalk Detour Map (PDF)

Email Updates

If you would like to receive detailed weekly email updates on this project, please enter your email address in the field below (email updates set to begin the week of Jan. 12):

Powered byEMF Online Order Form

Lafayette Street Interchange Project/
U.S. Route 50 (Whitton Expressway) Roadway Improvements
Community Briefing - Discussion of Whitton Expressway Traffic Management Plan
 
The Missouri Department of Transportation held a community briefing on Thursday, May 29, 2014 to discuss the traffic management plan during improvements to the Lafayette Interchange/Whitton Expressway (Route 50) in Jefferson City.

Here were the materials that were presented at the meeting. They can be downloaded below in a PDF format:

Whitton Expressway Construction Phase Maps (PDF)

Construction Phase One
Construction Phase Two

Construction Phase Three (Revised)

Construction Phase Four
Construction Phase Five

Construction Phase Six

GroundLafayette1219250Notable Project Press Releases

 

 

 

 

 

 
District Map
Central District
spacer
Traveler Information
Traveler Map
map
call, cell, mobile, phone iconText Alerts - Sign Up!
spacer
Quick Links
Your Local Area Engineer
Report a Road Concern
On the Move
spacer
Your Local MoDOT
Get your local district information.
Districts Map
Northwest Northeast Kansas City Central St. Louis Southwest Southeast
About Us
How Do I...
Contact Us
Missouri Department of Transportation
Central Office
105 W. Capitol Avenue
Jefferson City, MO 65102
1-888-ASK-MODOT (275-6636)
1-866-831-6277 (Motor Carrier Services)
Drivers License Offices
horz_bar
| | |
Missouri State Government
© 2013 Missouri Department of Transportation. All Rights Reserved.   Privacy Policy.
 
 
Howard Boone Cooper Morgan Camden Laclede Pulaski Phelps Dent Moniteau Miller Cole Crawford Washington Maries Callaway Osage Gasconade Northwest Northeast Kansas City Southwest Southeast Central St. Louis iTunes Android