Construction VE
Beginning in late 1989 (Federal Fiscal Year 1990) the department
added a
construction value engineering program. Contractors
submit Value
Engineering Change Proposals (VECP'S) for department review and
approval.
If accepted, the contractor and the department
share the total savings
on a 50/50 basis. Beginning in 2007, contractors can submit Practical
Design Value Engineering Change Proposal (PDVECP).
If accepted, PDVECP savings are split 25% Contractor/75%. MoDOT
PDVECP typically consist of an existing feature that could remain a part of
the final project, for example, exisiting pavement, an existing pipe, etc. See file below for a summary of the Federal Fiscal Year 2007 Construction VECP's and PDVECP's.
VECP's by Engineering Policy Guide Categories 
200 Geometric
300 Bases
400 Flexible Pavement
500 Rigid Pavement
600 Incidental Construction
700 Structures and Hydraulics
800 Roadside Development
900 Traffic Control
1000 Materials
1100 Maintenance Materials
MoDOT's Value Engineering