AUDRAIN COUNTY
Route W - Job #3S2010E- Economic Recovery Project
- Resurfacing from Route V in Vandalia to Route K east junction, 7 miles
- Completed
- Project Manager Tom Batenhorst, P.E., 573-248-2454
Route C - Job #3S2010I – Economic Recovery Project
- Resurfacing from Route 6 in Ewing to Route 61 near LaGrange, 12.6 miles
- Completed
- Project Manager Rick Domzalski, P.E., 573-248-2579
Route K - Job #3S2010G – Economic Recovery Project
- Resurfacing from Route E to Route 6 in LaBelle, 8.2 miles
- Completed
- Project Manager Rick Domzalski, P.E., 573-248-2579
Business Route 61 - Job #3S2010H – Economic Recovery Project
- Resurfacing from Route 61 to Route B in LaGrange, 1.8 miles
- Completed
- Project Manager Rick Domzalski, P.E., 573-248-2579
Route E - Job #3S2010C – Economic Recovery Project
- Resurfacing from Route O North junction to Route UU in Silex, 10.9 miles
- Completed
- Project Manager Tom Batenhorst, P.E., 573-248-2454
Route UU - Job #3S2010F – Economic Recovery Project
- Resurfacing from Route Z to Route E in Silex, 4.5 miles
- Completed
- Project Manager Tom Batenhorst, P.E., 573-248-2454
MARION COUNTY
Business Route 61 - Job #3M0049
- Resurfacing from just north of Route BB to just north of Routes 24 and 61 in Palmyra, 2.8 miles
- Completed
- Project Manager Rick Domzalski, P.E., 573-248-2579
Route C - Job #3M0050
- Resurfacing from Route Z West junction to Route 168 near Palmyra, 9.8 miles
- Completed
- Project Manager Rick Domzalski, P.E., 573-248-2579
Route 24/61 - Job #J3P2158 - Economic Recover Project
- Bridges over North Fabius River - Rehabilitate both north and south bound bridges just north of Route 6 near Taylor
- Completed
- Project Manager Chris Knapp, P.E., 573-248-2586
MONTGOMERY COUNTY
Route 19 - Job #3P2192– Economic Recovery Project
- Resurfacing from just north of Montgomery City to about two miles south of I-70, 8.8 miles
- Completed
- Project Manager Chris Knapp, P.E., 573-248-2586
PIKE COUNTY
Route Y - Job #3S2010D – Economic Recovery Project
- Resurfacing from Business Route 61 in Bowling Green to County Road 486, 2.4 miles
- Completed
- Project Manager Tom Batenhorst, P.E., 573-248-2454
WARREN COUNTY
Route A/B - Job #3P2172– Economic Recovery Project
-
Route A/B Interchange/South Outer Road - Intersection (rebuilding the bridge) and outer road improvements near Flying J Restaurant
- Completed
-
Project Manager Chris Knapp, P.E., 573-248-2586
|